County: Sandoval CPB No: XP-00F642 Funding: STAG<br />
San Felipe Pueblo of Project Amount $382,000.00<br />
CPB Manager: DuBois, Stephanie Grant Amount: $382,000.00<br />
Population Served by This Project 200 Loan Amount: $0.00<br />
Project Phase:<br />
Problem:<br />
Solution:<br />
Project:<br />
Grant Agreement Phase<br />
Not meeting permit discharge requirements<br />
Upgrades to the WWTP<br />
Wastewater <strong>Infrastructure</strong> Improvements<br />
Fund Balance: $382,000.00<br />
In FY 2010, Congress appropriated $388,000 for San Felipe for Wastewater infrastructure improvements.<br />
$222,765 has been awarded as XP-00F642. This funding is associated with pre-award costs. For the remaining<br />
$165,235 revolves around upgrades to the WWTP. 5-15-12 EPA denied San Felipe Pueblo's source of matching<br />
funds. 11-28-12 EPA submitted NEPA project file documentation.12-10-12 CPB requested Pueblo to provide<br />
details for WWTP upgrades to determine if project qualifies for a categorical exclusion. EPA approved pre-award<br />
costs and instructed Pueblo to submit pay request and invoices directly to EPA for reimbursement. 12-17-12 Pinu'u<br />
Stout of Pueblo stated that project consists of installing membrane casettes into existing basins.<br />
County: Sandoval<br />
Sandoval County<br />
CPB No: CWSRF 006G<br />
Funding:<br />
Project Amount<br />
CWSRF<br />
$1,220,000.00<br />
CPB Manager: Bishop, David Loan Amount: $0.00<br />
Population Served by This Project 731 Grant Amount: $1,220,000.00<br />
Project Phase: Construction Fund Balance: $811,167.97<br />
Problem:<br />
Solution:<br />
Project:<br />
Existing wastewater treatment plant does not meet NPDES permit requirements.<br />
Upgrade wastewater treatment plant so effluent will meet NPDES permit requirements.<br />
Construction of a new WWTP for the Village of Cuba<br />
to plan, design, construct and improve the wastewater treatment system in Cuba in Sandoval county. 1/23/12 CPB<br />
issues FONSI and Final Determination Letter. 2/29/12 CPB reviews and approves Revised Plans & Specs to<br />
advertise for bids. Bids were advertised 2/12/12, prebid conference will be on 2/28/12 and bids will be opened on<br />
3/13/12. 6/5/12 Low bidder is TLC; Given NTP on 4/30/12. 12/10/12 Construction is 56% complete.<br />
County: Sandoval<br />
Santa Ana, Pueblo of<br />
CPB No: TIF 12-7-DC PIF 10<br />
Funding:<br />
Project Amount<br />
TIF<br />
$1,200,000.00<br />
CPB Manager: DuBois, Stephanie Grant Amount: $1,200,000.00<br />
Population Served by This Project 10 Loan Amount: $0.00<br />
Project Phase:<br />
Problem:<br />
Solution:<br />
Project:<br />
Design Phase<br />
lack of housing<br />
construct site improvements for planned subdivision<br />
Pueblo of Santa Ana Adobe Estates Subdivision<br />
Fund Balance: $1,200,000.00<br />
$1,200,000 for engineering and construction of wet and dry utilities, sanitary sewer lift station, storm drainage,<br />
roadway, earthwork and building pads for the Adobe Estates Subdivision project. 9-27-12 grant agreement was<br />
executed by the Indian Affairs Department (IAD).11-14-12 CPB met with Santa Ana Pueblo representative who<br />
submitted RFP, ranking and engineering agreement with WH Pacific. 11-14-12 CPB notified IAD that they may<br />
proceed with executing the notice of obligation (NOO) for WH Pacific's contract with Santa Ana Pueblo, $75,500.<br />
12-11-12 Pueblo asked IAD for verification that NOO was approved.<br />
53