County: San Juan<br />
Navajo Nation, Counselor Chapter<br />
CPB No: TIF 12-14-DC PIF 8<br />
Funding:<br />
Project Amount<br />
TIF<br />
$417,678.00<br />
CPB Manager: Telmo, Andrea Grant Amount: $417,678.00<br />
Population Served by This Project 110 Loan Amount: $0.00<br />
Project Phase: Grant Agreement Phase Fund Balance: $417,678.00<br />
Problem:<br />
Solution:<br />
Project:<br />
Only 17% of the population of the Counselor Chapter has electricity.<br />
A 13-mile powerline extension will be constructed to provide power to 110 people (29 homes out<br />
of a total of 310 homes in need of power) in the Day Mesa area of the Chapter.<br />
Navajo Nation, Counselor Chapter Phase II (Day Mesa) Power Extension Line<br />
Awaiting executed Grant Agreement.<br />
County: San Juan<br />
Navajo Nation, White Rock Chapter<br />
CPB No: TIF 12-20-PG PIF 3<br />
Funding:<br />
Project Amount<br />
TIF<br />
$600,000.00<br />
CPB Manager: Bishop, David Grant Amount: $600,000.00<br />
Population Served by This Project 25 Loan Amount: $0.00<br />
Project Phase:<br />
Grant Agreement Phase<br />
Fund Balance: $600,000.00<br />
Problem: Chapter has limited or no potable water<br />
Solution: Plan, design and construct water infrastructure.<br />
Project: Navajo Nation, White Rock Chapter Eastern Navajo Water Pipeline Ph 6f &6g<br />
Cutter lateral Phase 6F & 6G part of Navajo Gallup Water Supply project. 9/27/12 no activity to date. 11/9/12 grant<br />
agreement returned funds will be used for Design of Cutter Lateral Phase 6f and 6g. 12/6/12 Navajo Nation Water<br />
Resource Department has requested to act as fiscal agent for Chapter; IAD to review.<br />
County: San Juan<br />
Northstar (Formerly Southside WUA)<br />
CPB No: WTB-70<br />
Funding:<br />
Project Amount<br />
WTB<br />
$1,432,552.00<br />
CPB Manager: Bishop, David Grant Amount: $1,432,552.00<br />
Population Served by This Project 3,976 Loan Amount: $0.00<br />
Project Phase:<br />
Problem:<br />
Solution:<br />
Project:<br />
Grant Agreement Phase<br />
issues with water system<br />
install tank, lines, pump station<br />
Regional Water System<br />
Fund Balance: $123,029.17<br />
WTB #70 ($1,432,552) and WTB #94 ($2M) design and construction of water system improvements for the<br />
Animas Regional Domestic Water Coalition, 5/26/10 CPB reviews and approves plans and specifications for the<br />
construction of 16 mi of water pipeline, 2 tanks, pump station, ARV's and appurtenances. 5/25/12 still working on<br />
finalizing close out documents. About $100,000 is owed to contractor Merryman Excavation, but have not been<br />
able to contact the contractor. P&S for Ph 2 have been completed by SMA. However, there has been a falling out<br />
with SMA. Northstar will hire Cheney Walter Echols for the bidding and construction management of Ph 2 by<br />
summer 2012. Estimated construction costs for Ph 2 is about $1.8M. As of 6-30-12 contract with NMFA expired.<br />
NMFA will now administer project. 12/10/12 NMFA MOU expired June 30, 2012. No activity by CPB pending new<br />
MOU.<br />