County: Grant<br />
Silver City, Town of<br />
CPB No: XP-96672001-1<br />
Funding:<br />
Project Amount<br />
STAG<br />
$967,900.00<br />
CPB Manager: Deal, Steven Grant Amount: $967,900.00<br />
Population Served by This Project 10,315 Loan Amount: $0.00<br />
Project Phase: Construction Fund Balance: $501,219.53<br />
Problem:<br />
Solution:<br />
Project:<br />
Upgrades and replacements of key Wastewater Treatment Plant components are needed.<br />
The sludge digester, electrical systems and sludge reroute line projects have been completed.<br />
The City is in the process of replacing the bar screen to use the remaining funds.<br />
Wastewater Treatment Plant Improvements<br />
Sludge Digester and Electrical upgrade phases have been completed; pipeline re-route is ongoing as of 7/15/11<br />
with expected completion in early August 2011; approximately 50% of federal funds have been expended with two<br />
requests pending revised documentation; most recent work was done to add a sludge reroute line to the<br />
Wastewater Treatment Plant. 1/5/12 SD Bar screen plans have been reviewed and sent back with comments. Full<br />
expenditure of funds should occur before the end of 2012. SD 7/9/12 Bar screen upgrade project has bid and is in<br />
construction. SD 12/11/12<br />
County: Hidalgo<br />
Rodeo MDWC & SMWA<br />
CPB No: WTB-132<br />
Funding:<br />
Project Amount<br />
WTB<br />
$382,781.00<br />
CPB Manager: Deal, Steven Grant Amount: $382,781.00<br />
Population Served by This Project 101 Loan Amount: $0.00<br />
Project Phase: Construction Fund Balance: $218,824.63<br />
Problem:<br />
Solution:<br />
Project:<br />
The water system is under a NMED Cooperative Compliance Order for excessive fluoride in their<br />
water.<br />
Install a reverse osmosis system to remove fluoride to bring the system into compliance.<br />
Storage Conveyance and Delivery<br />
the Rodeo Fluoride Water Treatment Project which will treat the existing water sources with a reverse osmosis<br />
system to remove fluoride and satisfy a Cooperative Compliance Order to which the Rodeo Mutual Domestic Water<br />
Consumers and Mutual Sewage Works Association is a party; project is in the final stages of completion to help<br />
bring Rodeo into compliance with Drinking Water Standards. 1/5/12 SD Change Order #7 was recommended to<br />
NMFA to complete the project. SD 7/9/12<br />
NMFA MOU expired June 30, 2012. No activity by CPB pending new MOU. 12/11/12 SD<br />
19