County: Taos<br />

El Valle De Los Ranchos<br />

CPB No: SAP 12-1374-STB<br />

Funding:<br />

Project Amount<br />

SAP Grants<br />

CPB Manager: Telmo, Andrea Grant Amount: $50,000.00<br />

Population Served by This Project 200 Loan Amount: $0.00<br />

Project Phase: Grant Agreement Phase Fund Balance: $50,000.00<br />

Problem: The District has an ongoing multi-phase project to expand sewer service in its service area to<br />

eliminate septic systems in congested areas with high groundwater.<br />

Solution: The project will extend the collection system to provide sewer service to more of the District's<br />

service area.<br />

Project: to design and construct phase 2C wastewater system improvements for El Valle de los<br />

Ranchos water and sanitation district in Taos county.<br />

Awaiting executed grant agreement. Engineer Abeyta Engineering is under contract. Funding will be used to design<br />

and construct Phase 2C-2 which will connect to Phases 2B-2 and 2B-3 which are funded by CWSRF 014.<br />

County: Taos<br />

Lower Des Montes MDWCA<br />

CPB No: RIP 2012-08<br />

Funding:<br />

Project Amount<br />

RIP Loans<br />

$0.00<br />

$60,000.00<br />

CPB Manager: Telmo, Andrea Grant Amount: $0.00<br />

Population Served by This Project 300 Loan Amount: $60,000.00<br />

Project Phase: Design Phase Fund Balance: $31,003.00<br />

Problem: Existing water system infrastructure is aged or undersized. Some facilities are 40-50 years old,<br />

storage capacity is insufficient, distribution system has low pressure, and undersized facilities limit<br />

expansion of service area.<br />

Solution: Design Phase 1 of water system improvements, including new water storage tank, waterlines,<br />

booster pump station, and PRV station; rehabilitation of existing water storage tank and well<br />

house; and installation of new meters and meter upgrades.<br />

Project: Design of Phase 1 water system improvements, including construction of new water<br />

storage tanks, waterlines, booster pump station, and PRV station; rehabilitation of existing<br />

water storage tank and well house; and installation of new water meters and meter<br />

upgrades.<br />

PER was funded with CDBG planning grant. CPB recommended approval of PER to DFA on 9/29/2011. Design in<br />

progress. 12/19/2012<br />

County: Taos<br />

Questa, Village of<br />

CPB No: ARRA CWSRF 10L<br />

Funding:<br />

Project Amount<br />

CWSRF<br />

$90,000.00<br />

CPB Manager: Kahl, Judi Grant Amount: $0.00<br />

Population Served by This Project 1,770 Loan Amount: $90,000.00<br />

Project Phase:<br />

Problem:<br />

Solution:<br />

Project:<br />

Construction<br />

Fund Balance: $60,000.00<br />

The Village of Questa needs a completely new WWTP<br />

The funding is being used to construct a completely new extended aeration WWTP.<br />

WWTP Improvements<br />

Project is a complete rebuilding of the wastewater treatment plant for the Village of Questa. The project is<br />

approximately 75% complete as of June 2011. Scheduled completion date is November 2011. Project is 93%<br />

complete as of the end of August 2011. Project is 97% complete and just waiting for final piece of equipment so it<br />

can be finished and the plant put on line. Completion date currently the end of July 2012. 5/30/2012. Project<br />

construction is complete as of November 2012. The final change order and closeout documents are pending as of<br />

12-5-12.<br />