County: Taos<br />

Taos, County of<br />

CPB Manager: Telmo, Andrea<br />

CPB No: RIP 2009-01<br />

Funding:<br />

Project Amount<br />

Grant Amount:<br />

RIP Loans<br />

$525,000.00<br />

Population Served by This Project 32,937 Loan Amount: $500,000.00<br />

Project Phase: Design Phase Fund Balance: $442,024.48<br />

Problem:<br />

Solution:<br />

Project:<br />

Taos County would like to expand their solid waste operations and provide recycling facilities to<br />

better serve the entire County.<br />

Construct new solid waste and recycling facilities.<br />

to plan, design and construct a new facility for the Taos County Solid Waste Department<br />

$500,000 RIP loan to plan, design and construct a new facility for the Taos County Solid Waste Department.<br />

Project has been designed, but additional funds are needed for construction.<br />

County: Taos<br />

Taos, Town of<br />

CPB Manager: Kahl, Judi<br />

CPB No: ARRA CWSRF 15L<br />

Funding:<br />

Project Amount<br />

Grant Amount:<br />

CWSRF<br />

$0.00<br />

$1,200,000.00<br />

Population Served by This Project 5,716 Loan Amount: $1,200,000.00<br />

Project Phase: Construction Fund Balance: $19,668.86<br />

Problem:<br />

Solution:<br />

Project:<br />

$0.00<br />

The town of Taos needed upgrades to their WWTP to meet their permit limits.<br />

The town rebuilt portions of their existing plant and added a membrane filtration system and solar<br />

panels.<br />

Phase 2 & 3 WWTP upgrades to wastewater treatment plant<br />

Project construction is complete. There will be one additional pay request for project closeout. Final pay request<br />

has been received and is ready for payment upon receipt of closeout documents. 12/3/12.<br />

County: Taos<br />

Tres Piedras MDWCA<br />

CPB No: 2749-PG<br />

Funding:<br />

Project Amount<br />

NMFA-PG<br />

$50,000.00<br />

CPB Manager: Telmo, Andrea Grant Amount: $50,000.00<br />

Population Served by This Project 315 Loan Amount: $0.00<br />

Project Phase: Planning Phase Fund Balance: $50,000.00<br />

Problem:<br />

Solution:<br />

Project:<br />

Water system is in need of improvements, including but not limited to a new water supply well,<br />

replacement of aging and/or undersized waterlines, construction of new waterlines to expand the<br />

service area, and distribution system improvements to address areas with low water pressure.<br />

Complete PER to identify and prioritize needs and determine most cost-effective project.<br />

Preliminary Engineering <strong>Report</strong> for water system improvements.<br />

RFP advertised 10/11/12. Proposals due 11/13/12. Selection of engineer in progress.<br />

County: Taos<br />

Union Del Llano MDWCA<br />

CPB No: 2651-PG<br />

Funding:<br />

Project Amount<br />

NMFA-PG<br />

$50,000.00<br />

CPB Manager: Telmo, Andrea Grant Amount: $50,000.00<br />

Population Served by This Project 484 Loan Amount: $0.00<br />

Project Phase: Planning Phase Fund Balance: $50,000.00<br />

Problem: Llano San Juan MDWCA & Cuchilla del Llano MDWCA have aging, deteriorating, and undersized<br />

infrastructure.<br />

Solution: Llano San Juan & Cuchilla del Llano are merging to form Union del Llano; a PER will be<br />

completed to identify the infrastructure needs and propose a project to address these needs.<br />

Project: Water System Improvements PER<br />

PER scoping/kickoff meeting held 4/10/2012. PER in progress. 12/19/2012<br />