County: Cibola<br />

Bluewater Acres DWU<br />

CPB No: SAP 12-1340-STB<br />

Funding:<br />

Project Amount<br />

SAP Grants<br />

CPB Manager: Bishop, David Grant Amount: $50,000.00<br />

Population Served by This Project 371 Loan Amount: $0.00<br />

Project Phase:<br />

Problem:<br />

Solution:<br />

Project:<br />

Planning Phase<br />

issues with security<br />

install fencing & security cameras<br />

Well #2 Renovation<br />

$0.00<br />

Fund Balance: $50,000.00<br />

to purchase, plan, design construct, install, equip and furnish improvements, including a building, a garage, fencing<br />

and security cameras, for the Bluewater Acres domestic water users association in Cibola County. 8-20-12<br />

Bluewater Acres will utilize funds toward refurbishment of existing well/piping/electrical and coat the well house.<br />

Will provide quotes to CPB. 11/19/12 quotes for electrical work reviewed and approved. 12/7/12 quotes for well<br />

upgrade received and approved.<br />

County: Cibola<br />

Cebolleta Land Grant<br />

CPB No: SAP 12-1358-STB<br />

Funding:<br />

Project Amount<br />

SAP Grants<br />

CPB Manager: Bishop, David Grant Amount: $50,000.00<br />

Population Served by This Project 100 Loan Amount: $0.00<br />

Project Phase: Planning Phase Fund Balance: $38,722.20<br />

Problem:<br />

Solution:<br />

Project:<br />

<strong>New</strong> wastewater lagoons are not properly permitted with NMED Ground Water Quality Bureau.<br />

Obtain ground water discharge permit from NMED GWQB<br />

Waste water treatment system<br />

$50,000 to plan, design and construct a wastewater treatment system for the Cebolleta land grant in Cibola county.<br />

10/30/12 DB reviewed and approved engineering agreement. 12/7/12 Medina Consulting is working with GWQB to<br />

finalize discharge permit and getting quotes to make minor repairs to lift station.<br />

County: Cibola<br />

Grants, City of<br />

CPB No: WTB-152<br />

Funding:<br />

Project Amount<br />

WTB<br />

$0.00<br />

$200,000.00<br />

CPB Manager: Bishop, David Grant Amount: $200,000.00<br />

Population Served by This Project 9,182 Loan Amount: $0.00<br />

Project Phase:<br />

Problem:<br />

Solution:<br />

Project:<br />

Grant Agreement Phase<br />

Aging infrastructure needs to be replaced.<br />

Replace infrastructure<br />

Water Storage, Conveyance and Delivery<br />

Fund Balance: $200,000.00<br />

to plan, design and construct utility improvements to First and Second streets and to Roosevelt avenue in Grants in<br />

Cibola county. 10/5/11 P&S 60% complete and have been reviewed by CPB. Waiting for the submittal of the Final<br />

P&S for review. 3/2/12 checking with engineer to find out when Final P&S will be submitted to CPB for review.<br />

6/6/12 need final plans and specs. 12/10/12 NMFA MOU expired June 30, 2012. No activity by CPB pending new<br />

MOU.<br />

County: Cibola<br />

Grants, City of<br />

CPB No: WTB-194<br />

Funding:<br />

Project Amount<br />

WTB<br />

$842,191.00<br />

CPB Manager: Bishop, David Grant Amount: $842,191.00<br />

Population Served by This Project 9,182 Loan Amount: $0.00<br />

Project Phase:<br />

Problem:<br />

Solution:<br />

Project:<br />

Grant Agreement Phase<br />

Aging infrastructure needs to be replaced<br />

Replace infrastructure.<br />

Water Storage, Conveyance and Delivery<br />

Fund Balance: $195,843.54<br />

water lines, appurtenances, new fire hydrants, reconnection of laterals and reconnection to water utility distribution<br />

infrastructure. 11/2/11 Project in construction and currently about 80% complete. 3/7/12 Construction has been<br />

suspended during the winter months due to weather conditions. Eng. expects construction will resume in late March<br />

2012. 6/6/12 Construction is completed, waiting on close out documentation. 12/10/12 NMFA MOU expired June<br />

30, 2012. No activity by CPB pending new MOU.<br />

5