8. Estimated System Costs RTC SR-160 <strong>Corridor</strong> <strong>Study</strong><br />

Alternatives 1 (2015) and 1 (2025) which vary only by the level of conventional bus transit<br />

provided have the same lower bound capital cost estimate which assumes there is no need<br />

to purchase additional 40’ coaches for conventional bus services. The roughly $2.5 million<br />

difference in the upper bound estimate for these two alternatives reflects the additional<br />

costs of 40’ coaches in Alternative 1 (2025) which provides a greater level of conventional<br />

bus transit services.<br />

8.1.3 Alternative 2 – Moderate Growth<br />

Like Alternative 1 – High Growth, Alternative 2 – Moderate Growth costs are provided as<br />

ranges reflecting variability in two cost elements: 1) the need to purchase additional 40<br />

foot coaches, and 2) how the property for Park & Ride facilities would be acquired from<br />

BLM. EXHIBIT 8-3 provides an estimate of the capital costs for Alternative 2 – Moderate<br />

Growth. Capital costs for Alternative 2 increase dramatically in 2025 - the year during<br />

which BRT service is implemented. Like costs for Alternative 1, capital costs for Alternative<br />

2 are presented in total for each horizon year, and include the costs for investment that<br />

may have occurred in an earlier year. For example, costs for Alternative 2 (2025) are<br />

inclusive of costs required to implement Alternative 2 in 2015.<br />

EXHIBIT 8-3: Alternative 2 – Moderate Growth Capital Costs<br />

System Elements<br />

Alternative 2 –<br />

2008<br />

(’06 $)<br />

Alternative 2 –<br />

2015<br />

(’06 $)<br />

Alternative 2 –<br />

2025<br />

(’06 $)<br />

Guideway Costs<br />

Re-striping/Transit Signal Priority -- -- $500,000<br />

Acquisition -- -- --<br />

Subtotal: Guideway Costs -- -- $500,000<br />

Vehicle Costs<br />

40’ Coaches $0 - $3,500,000<br />

(10 coaches)<br />

$0 - $5,950,000<br />

(17 coaches)<br />

$0 - $4,200,000<br />

(12 coaches)<br />

Station Costs<br />

BRT Vehicles (8 vehicles) -- -- $10,480,000<br />

Subtotal: Vehicles $0-$3,500,000 $0 - $5,950,000<br />

$10,480,000 -<br />

$14,680,000<br />

Park & Ride Stations (2) -- -- $7,000,000<br />

Land Acquisition -- -- $0 - $28,612,000<br />

Intermediate Stations (3) -- -- $3,750,000<br />

Surface Parking (at P&R stations) -- -- $1,200,000<br />

Other Costs<br />

Bus Stop Amenities $8,000 $26,000 $27,000<br />

Subtotal: Station Costs $8,000 $26,000<br />

$11,977,000 -<br />

$40,589,000<br />

Maintenance/Storage Costs -- -- $500,000<br />