JT5 Operator’s <strong>Manual</strong> Prepare - 59<br />

Plan Bore Path<br />

Minimum Depth<br />

Because you must bend pipe gradually, entry pitch and<br />

bend limits determine how deep the pipe will be when<br />

it becomes horizontal. This is called the minimum<br />

depth.<br />

• To reduce minimum depth (D1), reduce entry<br />

pitch. This also decreases setback.<br />

• To increase minimum depth (D2), increase entry<br />

pitch. This also increases setback.<br />

Bore Path Calculator<br />

Entry pitch, setback, and minimum depth work together with bend limits to determine the bore path. To find<br />

the setback (B) and entry pitch (A) that will take you to the desired minimum depth (D), use the chart<br />

below.<br />

Minimum depth (D) Entry pitch (A) Setback (B) Depth to begin steering (S)<br />

2’ 0" (0.6 m) -18% 17’ 4" (5.3 m) 0’ 11" (0.28 m)<br />

2’ 4" (0.7 m) -20% 18’ 8" (5.7 m) 1’ 0" (0.30 m)<br />

2’ 9" (0.8 m) -22% 19’ 11" (6.1 m) 1’ 1" (0.33 m)<br />

3’ 1" (0.9 m) -24% 21’ 2" (6.5 m) 1’ 2" (0.36 m)<br />

3’ 6" (1.1 m) -26 22’ 5" (6.8 m) 1’ 3" (0.38 m)<br />

3’ 11" (1.2 m) -28 23’ 8" (7.2 m) 1’ 4" (0.41 m)<br />

4’ 5" (1.4 m) -30 24’ 11" (7.6 m) 1’ 5" (0.43 m)<br />

IMPORTANT: Numbers in table based on 70’ (21.3 m) minimum bend radius, beacon housing, EZ-<br />

Connect, connector, transition sub, and 1/3 of first drill pipe (L, totaling 5’ [1.5 m]) in the ground before<br />

steering.<br />