<strong>Prigorodnoye</strong> <strong>Export</strong> <strong>Terminal</strong> <strong>Port</strong> <strong>Regulations</strong> Rev 01<br />
27.3 Vessel moving Out of Position whilst alongside<br />
Where a ship has moved out of position a sufficient distance to either;<br />
• activate the ESD system, or<br />
• warrant corrective action in the opinion of the Loading Master, loading will be stopped,<br />
loading arm(s) drained, purged and disconnected prior to repositioning the ship.<br />
Whenever repositioning of a ship is required, pilot and tugs must be in attendance, the ship’s<br />
engine readied, and the shore mooring gang on station. The pilot will remain onboard.<br />
28 LNG Pre Loading Operations<br />
28.1 Gangway<br />
On completion of mooring the Loading Master and ship’s Master will confirm to the Loading<br />
Master that the tanker is securely moored (“All Fast”), the main engine steam stop valve is<br />
shut and the turning gear has been engaged (“MESSVSTGE). "No Smoking" and "Authorised<br />
access" notices (to be provided by the ship) are to be prominently displayed at the gangway<br />
position. At this point the terminal may be advised the gangway can be lifted onboard.<br />
A member of the ship’s crew must be in attendance to guide and position the gangway steps<br />
onto the ship’s deck. Before boarding the tanker a Responsible Ship’s Officer must agree with<br />
the Loading Master that the gangway is safely in place and boarding of shore personnel can<br />
take place.<br />
The vessel’s engines are to remain in readiness with the warming through system in operation<br />
throughout the time alongside.<br />
28.2 Connecting ESD/Communications Cables<br />
The ship shore link (SSL) shall be connected by a member of the ship crew and verified by the<br />
Loading Master to check correct.<br />
28.3 Mooring Integrity & Safety Checks<br />
Prior to connecting the loading arms and/or commencement of the ‘Pre-loading meeting’ the<br />
Loading Master shall together with a Responsible Ship’s Officer check and confirm that all<br />
moorings are tight, brakes properly hardened up and winches are out of gear. On completion<br />
of confirming mooring integrity, connection of loading arms may proceed.<br />
In the process of conducting the mooring integrity check other safety checks as per the<br />
ship/shore checklist, insofar as they can be confirmed at this stage, should be completed.<br />
28.4 Connecting Loading Arms<br />
0000-S-90-01-P-0207-00-E<br />
Page 52 of 101<br />
BM Code: EP.14.03.01.09