<strong>Prigorodnoye</strong> <strong>Export</strong> <strong>Terminal</strong> <strong>Port</strong> <strong>Regulations</strong> Rev 01<br />

purging shall be repeated until the O2 content is less than 1% by volume.<br />

28.7 Water Curtain<br />

Prior to connecting the loading arms to the ship's manifold valves the ship shall start up the<br />

water curtain at the manifold and all other deck protective systems for tank domes as<br />

required. Winter precautions shall be exercised when very low temperatures are experienced<br />

with trays to be in place with 25% water fill and overside water curtain sprays running. Should<br />

the deck freeze, the water supply may be shut off.<br />

Note the LNG tankers manifold water curtain is a separate issue to the availability of the<br />

vessel’s IMO standard water spray fire curtain. This should be drained to avoid icing issues<br />

but emergency pumps should be available at immediate notice in case of fire and emergency<br />

use.<br />

During the winter season utmost care is to be taken to avoid the following systems freezing.<br />

• Fire main.<br />

• Foam main.<br />

• Valve hydraulics.<br />

• Emergency escapes.<br />

• De-icing equipment.<br />

• Personnel ice contact issues.<br />

28.8 Gauging<br />

Before the ship's manifold valves are opened gauging of the ship's tanks will take place on all<br />

occasions, regardless of the status of the ship's tanks. This process is to be witnessed by the<br />

Responsible Ship’s Officer, the Loading Master, the independent cargo surveyor, as required,<br />

and any other individual with a recognised and legitimate interest in the loading operation.<br />

28.9 ESD Tests<br />

In addition to any tests that may be carried out by the vessel and terminal prior to the ship's<br />

arrival, the following Emergency Shutdown (ESD) tests shall be conducted in conjunction with<br />

each ship and shore at the start of loading as follows.<br />

• A “warm” ESD test, before cooldown, when both terminal and ship have confirmed<br />

ready for test, initiate by the Ship. A second “warm” ESD test, with loading arms still at<br />

ambient temperature, may be performed by the terminal if requested by the Loading<br />

Master, such as for first cargo loading after new build or refit.<br />

• An additional “cold” ESD test will be initiated by the <strong>Terminal</strong>, after cooldown of the<br />

loading arms. This is to confirm all valves still close correctly in the fully refrigerated<br />

condition. This test will be performed with prior notice, giving a standby advice, agreed<br />

readiness, under a countdown and the closing timings for the ship and shore valves<br />

are to be recorded. This “cold” ESD test, with loading arms cooled down to LNG<br />

temperature, may also be initiated on alternate loadings, by the ship, if deemed so<br />

required.<br />

• Requirements to test ESD1 (loading/manifold valve and pump trip test) and ESD2<br />

(loading/manifold valve, pump trip and loading arm emergency release test) shall be<br />

0000-S-90-01-P-0207-00-E<br />

Page 54 of 101<br />

BM Code: EP.14.03.01.09