• A higher capital expenditure over the extensi<strong>on</strong> period is assumed compared to case 1 due to costs<br />
that would be associated <strong>with</strong> starting or extending open pits.<br />
Operating Costs<br />
Operating costs included in the Adjusted Marda Model c<strong>on</strong>sist <strong>of</strong> salaries and labour, reagents and<br />
operating c<strong>on</strong>sumables, power, maintenance, general administrati<strong>on</strong> and flights and accommodati<strong>on</strong> for<br />
mine staff. The tables below shows the forecast operating costs per annum for the remaining life <strong>of</strong> mine.<br />
Marda Case 1<br />
Marda Project Case 1 31-Dec-13 31-Dec-14 31-Dec-15 31-Dec-16 31-Dec-17 31-Dec-18 31-Dec-19<br />
$ $ $ $ $ $ $<br />
Mining - 2,513,978 11,668,042 11,599,472 11,743,251 13,103,516 10,570,702<br />
Mining Equipment Lease Cost - 739,881 3,053,768 3,053,752 3,054,406 434,844 156,388<br />
Processing - 3,187,890 16,204,233 15,434,282 16,235,555 15,324,801 15,545,830<br />
General Administrati<strong>on</strong> - 1,033,549 4,176,206 4,186,622 4,257,236 4,364,912 2,308,722<br />
Total Project Cost - 7,475,298 35,102,249 34,274,128 35,290,448 33,228,073 28,581,642<br />
Source: The Adjusted Marda Model<br />
Marda Case 2<br />
Marda Project Case 2<br />
31-Dec-13 31-Dec-14 31-Dec-15 31-Dec-16 31-Dec-17 31-Dec-18 31-Dec-19 31-Dec-20 31-Dec-21<br />
$ $ $ $ $ $ $ $<br />
Mining - 2,513,978 11,668,042 11,599,472 11,743,251 13,103,516 11,668,042 11,668,042 5,570,702<br />
Mining Equipment Lease - 739,881 3,053,768 3,053,752 3,054,406 434,844 3,053,768 3,053,768 156,388<br />
Processing - 3,187,890 16,204,233 15,434,282 16,235,555 15,324,801 16,204,233 16,204,233 8,545,830<br />
General Administrati<strong>on</strong> - 1,033,549 4,176,206 4,186,622 4,257,236 4,364,912 4,176,206 4,176,206 2,308,722<br />
Total Project Cost - 7,475,298 35,102,249 34,274,128 35,290,448 33,228,073 35,102,249 35,102,249 16,581,642<br />
Source: The Adjusted Marda Model<br />
Capital Expenditure<br />
The table below shows the forecast capital costs per annum for the remaining life <strong>of</strong> mine.<br />
Marda Case 1<br />
Marda Project Case 1 31-Dec-13 31-Dec-14 31-Dec-15 31-Dec-16 31-Dec-17 31-Dec-18 31-Dec-19<br />
$ $ $ $ $ $ $<br />
Capital Expenditure - 38,155,619 1,761,294 1,407,438 357,438 5,953,438 (881,851)<br />
Source: The Adjusted Marda Model<br />
Marda Case 2<br />
31-Dec-13 31-Dec-14 31-Dec-15 31-Dec-16 31-Dec-17 31-Dec-18 31-Dec-19 31-Dec-20 31-Dec-21<br />
Marda Project Case 2<br />
$ $ $ $ $ $ $ $<br />
Capital Expenditure - 38,155,619 1,761,294 1,407,438 357,438 5,953,438 2,000,000 2,000,000 (881,581)<br />
Source: The Adjusted Marda Model<br />
Capital expenditure for the Adjusted Marda Model c<strong>on</strong>sists <strong>of</strong> the removal, refurbishment, relocati<strong>on</strong> and<br />
installati<strong>on</strong> <strong>of</strong> plant and equipment as well as infrastructure items including camp, roads and airstrip,<br />