BDO CORPORATE FINANCE (WA) PTY LTD<br />

<strong>Polymetals</strong> Mining Limited and Southern Cross Goldfields Limited<br />

Technical Specialist's Report<br />

Processing Circuit<br />

The key unit operati<strong>on</strong>s and equipment utilised for the processing facility are as follows:<br />

• Primary crushing using the existing track-mounted Terex-Pegs<strong>on</strong> jaw crusher relocated from<br />

Sandst<strong>on</strong>e.<br />

• Stacking c<strong>on</strong>veyors relocated from Sandst<strong>on</strong>e which allow stockpiling, or direct feeding the mill via a<br />

feed bin and apr<strong>on</strong> feeder.<br />

• Single stage milling in a proposed 4.27 m diameter SAG mill powered by a 1.25 MW motor. This mill<br />

will need to be sourced externally. Circuit classificati<strong>on</strong> using Warman 10" cycl<strong>on</strong>es sourced from<br />

Sandst<strong>on</strong>e.<br />

• Gravity gold recovery using a new Falc<strong>on</strong> gravity c<strong>on</strong>centrator. Recovery <strong>of</strong> gravity gold from<br />

c<strong>on</strong>centrate to be undertaken by intensive leaching in a new intensive leach reactor, and subsequent<br />

electrowinning in a new dedicated gravity cell.<br />

• CIL leaching using nine draft tube style mechanically agitated tanks in series. All tanks to be<br />

refurbished and relocated from Sandst<strong>on</strong>e. First tank to be leaching <strong>on</strong>ly and remaining eight tanks for<br />

leaching plus adsorpti<strong>on</strong> <strong>of</strong> gold to carb<strong>on</strong>.<br />

• Recovery <strong>of</strong> gold from carb<strong>on</strong> using an integral 1.5 t carb<strong>on</strong> capacity eluti<strong>on</strong> and electrowinning facility<br />

relocated from Sandst<strong>on</strong>e. Carb<strong>on</strong> reactivati<strong>on</strong> in a new horiz<strong>on</strong>tal diesel fired kiln.<br />

• Reagent mixing and distributi<strong>on</strong> systems, water systems, diesel storage all relocated from Sandst<strong>on</strong>e.<br />

4.1.8.4 Gold Recovery<br />

Based <strong>on</strong> an assessment <strong>of</strong> test work results <strong>of</strong> samples from ore sources treated in the first three years,<br />

AMC c<strong>on</strong>siders that the mean recovery will be approximately 1% lower than the predicted 95% as presented<br />

in the financial model. It is not possible to make predicti<strong>on</strong>s <strong>on</strong> the later years <strong>of</strong> the project <strong>with</strong>out additi<strong>on</strong>al<br />

test work <strong>on</strong> samples from these deposits.<br />

4.1.8.5 Plant Throughput<br />

Annual ore throughput in the financial model ramps up to 550 ktpa in the sec<strong>on</strong>d year <strong>of</strong> the project which is<br />

higher than the current plant design throughput <strong>of</strong> 480 ktpa as presented in the most recent engineering<br />

study. The design used a c<strong>on</strong>servative <strong>on</strong>-line utilisati<strong>on</strong> <strong>of</strong> 92% and AMC c<strong>on</strong>siders that there is potential to<br />

increase availability <strong>of</strong> the mill above this design figure after commissi<strong>on</strong>ing and ramp-up. There is<br />

insufficient comminuti<strong>on</strong> test informati<strong>on</strong> <strong>on</strong> ore types to be treated in the later years <strong>of</strong> the project to make a<br />

throughput predicti<strong>on</strong>.<br />

4.1.8.6 Capital Estimate Plant and Infrastructure<br />

Southern Cross has prepared a capital estimate for plant and infrastructure, based <strong>on</strong> informati<strong>on</strong> provided<br />

by independent technical specialists in November 2012. This estimate was prepared to an accuracy level <strong>of</strong><br />

±20% and included a 20% c<strong>on</strong>tingency. The Southern Cross capital estimate is presented in Table 4.4. The<br />

costs presented include the removal, refurbishment, relocati<strong>on</strong> and installati<strong>on</strong> <strong>of</strong> plant and equipment as<br />

well as infrastructure items including camp, roads and airstrip, buildings/work-shops, and water supply. A<br />

preliminary estimate for tailings storage requirements is also included.<br />