BDO CORPORATE FINANCE (WA) PTY LTD<br />

<strong>Polymetals</strong> Mining Limited and Southern Cross Goldfields Limited<br />

Technical Specialist's Report<br />

c<strong>on</strong>servative, best-guess estimates for costs <strong>of</strong> overhaul <strong>of</strong> existing equipment were used. Estimati<strong>on</strong> errors<br />

have been assigned (e.g. 30% for the Ravensthorpe flotati<strong>on</strong> banks) as there is a degree <strong>of</strong> uncertainty that<br />

the equipment will be available when the project receives the go-ahead. Preliminary engineering drawings<br />

for the plant were produced by LogiCamms, a small South Australian firm.<br />

The crushing plant and the eluti<strong>on</strong> plant and gold room have been included as leased equipment, <strong>with</strong> the<br />

lease charge included in operating budget. The plant does not c<strong>on</strong>tain a gold room or eluti<strong>on</strong> circuit therefore<br />

the functi<strong>on</strong> <strong>of</strong> stripping and regenerating carb<strong>on</strong> will be outsourced. Load-out and receiving facilities have<br />

been designed to permit removal <strong>of</strong> loaded carb<strong>on</strong> and return <strong>of</strong> regenerated carb<strong>on</strong> by truck-mounted<br />

tanks.<br />

A plant <strong>of</strong> comparable size and capacity built c<strong>on</strong>venti<strong>on</strong>ally using engineering and c<strong>on</strong>structi<strong>on</strong> c<strong>on</strong>tractors<br />

and new equipment could be expected to cost between $23M and $30M. Successful in-house c<strong>on</strong>structi<strong>on</strong><br />

will depend <strong>on</strong> <strong>Polymetals</strong> being able to obtain appropriate equipment for the estimated prices, and being<br />

able to retain the right skills to accomplish c<strong>on</strong>structi<strong>on</strong> and commissi<strong>on</strong>ing in the allotted time.<br />

AMC notes that some items <strong>of</strong> capital are estimated <strong>on</strong> the basis <strong>of</strong> the availability <strong>of</strong> sec<strong>on</strong>dhand<br />

equipment. A c<strong>on</strong>tingency allowance <strong>of</strong> $1M has been made in case the sec<strong>on</strong>dhand equipment is not<br />

available.<br />

AMC notes that in an ASX announcement dated 29 January 2013 <strong>Polymetals</strong> quoted a capital cost for the<br />

project <strong>of</strong> $26.6M. <strong>Polymetals</strong> advised that this was in fact the maximum pre-producti<strong>on</strong> negative cash flow.<br />

This is c<strong>on</strong>sistent <strong>with</strong> the financial model reviewed for Mt Boppy project.<br />

Table 3.3<br />

Capital Estimate for Mt Boppy Redevelopment<br />

Area<br />

Capex<br />

(A$)<br />

Estimated<br />

Error<br />

(%)<br />

C<strong>on</strong>tingency<br />

(A$)<br />

Leased<br />

(in Opex)<br />

(A$)<br />

Tailings dam 2,087,947 15 316,442 - -<br />

ROM pad 50,000 25 12,500 - -<br />

3.1.5.5 Operating Costs<br />

Comments<br />

Crusher - - - 266,913 Old crusher to be removed, new equipment to be<br />

leased in Opex<br />

Grinding mills 1,841,775 16 289,095 - Placement <strong>of</strong> new mill, overhaul and alignment <strong>of</strong><br />

existing mill<br />

Leaching plant 1,209,429 17 211,028 - Includes 2 new thickeners, c<strong>on</strong>structi<strong>on</strong> and<br />

installati<strong>on</strong> <strong>of</strong> new MCC, some new agitators,<br />

overhaul <strong>of</strong> all pumps<br />

Eluti<strong>on</strong>, gold room - - - 363,250 Project calls for loaded carb<strong>on</strong> to be transported<br />

to White Dam for gold recovery<br />

Flotati<strong>on</strong> plant 450,000 30 135,000 - Existing plant (possibly Ravensthorpe) available<br />

for purchase and removal<br />

Reagent mixing 311,150 20 62,230 - -<br />

First fill (carb<strong>on</strong>, cyanide, 230,760 15 34,614 - -<br />

flotati<strong>on</strong> reagents)<br />

Services (air, water, power) 1,690,369 17 281,001 - Includes new water systems, including an RO<br />

plant<br />

Infrastructure 144,600 25 36,150 - -<br />

Camp 1,060,500 15 159,075 - new camp in Canbelego<br />

Vehicles - - - 737,750 vehicles to be leased<br />

EPCM (provided in-house) 1,465,175 23 330,614 - Salaried positi<strong>on</strong>s to be filled in-house where<br />

possible<br />

Owner's cost 1,190,000 10 119,000 - -<br />

TOTAL 11,731,705 1,986,749 1,367,913<br />

TOTAL (incl. C<strong>on</strong>tingency) 13,718,454 17<br />

Basic design parameters for the plant are shown in Table 3.4. The utilisati<strong>on</strong> values <strong>of</strong> 90% are c<strong>on</strong>servative<br />

and the gold recovery figure <strong>of</strong> 78% is supported by metallurgical test work.<br />