OceaniaAustralia - Perth International AirportEquipment: T1Quantity: 17Duration: The installations of systems will be staggered, commencing inNovember 2013, and for the contract to be completed byFebruary 2014. The first 2 systems are to be installed andconnected to Safecontrol Apron Management by Mid-November.Scope:With the expansion of Terminal 1, <strong>Safegate</strong> Group has entered intoa contract for the supply and commissioning of 17 x T1 Systems,and for the installation of Safecontrol Apron Management. TheSafecontrol Apron Management installation will also be connectedto 5 existing Safedock systems currently installed on siteClient objective: The client is interested in Safecontrol Apron Management for thefull automation of monitoring and docking aircraft.