Annex A – Scenario details<br />
A.I <strong>Offshore</strong> w<strong>in</strong>d power<br />
Scenarios<br />
An important task <strong>in</strong> the <strong>Offshore</strong>Grid project was the<br />
development of offshore w<strong>in</strong>d power scenarios. They<br />
are ma<strong>in</strong>ly based on the latest EWEA offshore w<strong>in</strong>d<br />
farms scenario [20] and on the onshore scenarios developed<br />
<strong>in</strong> TradeW<strong>in</strong>d [24], however data have been<br />
verified and new records have been added accord<strong>in</strong>g<br />
to the latest announcements of authorities and project<br />
developers. The database <strong>in</strong>cluded 373 records (w<strong>in</strong>d<br />
farm concepts) with a total capacity of over 180 GW<br />
<strong>in</strong> 15 countries (apart from Northern EU countries,<br />
also Norway and Russia has been considered). About<br />
50 GW of them are well advanced projects, where developers<br />
and/or <strong>in</strong>vestors are clear and the permitt<strong>in</strong>g<br />
procedure is ongo<strong>in</strong>g.<br />
FiGuRe 9.1: GeOGRaphic distRibutiOn OF identiFied OFFshORe pROjects<br />
On the basis of collected data, medium (2020) and<br />
long term (2030) scenarios have been developed. The<br />
ma<strong>in</strong> assumptions were:<br />
• The current proactive governmental policy towards<br />
the w<strong>in</strong>d farms will be cont<strong>in</strong>ued and jo<strong>in</strong>ed by<br />
other countries,<br />
• W<strong>in</strong>d farms licensed already (or well def<strong>in</strong>ed areas<br />
approved) and with advanced permitt<strong>in</strong>g procedure<br />
will be implemented before 2020, where the w<strong>in</strong>d<br />
farms operat<strong>in</strong>g <strong>in</strong> 2030 will be located <strong>in</strong> already<br />
identified zones,<br />
• Innovative concepts, like far (>60 km from shore)<br />
and deep (>60 m water depth) offshore, will not<br />
significantly contribute before 2030.<br />
The result<strong>in</strong>g scenario is presented <strong>in</strong> figure 9.1 and<br />
Table 9.1.<br />
106 <strong>Offshore</strong>Grid – F<strong>in</strong>al Report