03.12.2012 Views

Offshore Electricity Infrastructure in Europe - European Wind Energy ...

Offshore Electricity Infrastructure in Europe - European Wind Energy ...

Offshore Electricity Infrastructure in Europe - European Wind Energy ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

To that extent, a 1,000 MW ‘sp<strong>in</strong>e’ was established between<br />

the Idunn hub off Norway, the Dogger Bank hub<br />

off the UK and the IJmuiden hub off the Netherlands to<br />

Belgium 31 . Sensitivities were then performed on this<br />

<strong>in</strong>itial mesh around 32 :<br />

• the effectiveness of each of the l<strong>in</strong>ks with<strong>in</strong> the<br />

‘sp<strong>in</strong>e’,<br />

• add<strong>in</strong>g additional 1,000 MW offshore l<strong>in</strong>ks to<br />

Belgium and Sweden from the IJmuiden hub and<br />

Idunn hub respectively,<br />

• add<strong>in</strong>g additional 1,000 MW offshore l<strong>in</strong>ks to Belgium<br />

and Sweden from the Dutch and Norwegian onshore<br />

networks mesh connection po<strong>in</strong>ts respectively,<br />

• uprat<strong>in</strong>g the <strong>in</strong>dividual mesh l<strong>in</strong>ks to 2,000 MW,<br />

• removal of the ‘redundant’ hub-to-hub l<strong>in</strong>k between<br />

Idunn and IJmuiden from the base model.<br />

31 As can be seen from Figure 4.23, some parts of this ‘sp<strong>in</strong>e’ already existed <strong>in</strong> the model. As a result of the hub-to-hub analysis,<br />

the Dogger Bank hub was already connected to the Gaia hub <strong>in</strong> Germany, and the Idunn hub was already connected directly to<br />

the IJmuiden hub. Belgium, France, and Sweden were already connected to the Netherlands and Norway respectively via onshore<br />

re<strong>in</strong>forcements <strong>in</strong> the base model.<br />

32 Unlike for the direct <strong>in</strong>terconnections and the hub to hub connections the possible variations <strong>in</strong> mesh topology were not exhaustively<br />

modelled although several sensitivities assess<strong>in</strong>g the effect of changes <strong>in</strong> capacities, connection po<strong>in</strong>ts and removal of l<strong>in</strong>ks around<br />

the core <strong>in</strong>itial mesh and alternative mesh designs were analysed to arrive at the design presented here. (Further details of these<br />

sensitivity studies are represented <strong>in</strong> Annex D.III.I to this report).<br />

Whilst other alternative mesh designs are certa<strong>in</strong>ly possible and may even be more beneficial, it was felt that the proposed design<br />

demonstrated the benefit of a meshed offshore grid and was already sufficiently complex to make implementation by 2030 ambitious.<br />

<strong>Offshore</strong>Grid – F<strong>in</strong>al Report<br />

Figure 4.23 shows the overall f<strong>in</strong>al grid design after<br />

step 3 of the Direct Design Methodology for the North<br />

and Baltic Seas.<br />

Results – direct design<br />

Figure 4.24 shows the <strong>in</strong>frastructure costs (cumulatively)<br />

and the total system generation costs, and Figure 4.25<br />

shows the net benefit of the overall Direct Design.<br />

As can be seen from Figure 4.24, the cumulative <strong>in</strong>vestment<br />

cost curve (blue bars) for the Direct Design<br />

is reasonably l<strong>in</strong>ear for the direct <strong>in</strong>terconnectors. This<br />

reflects the discrete <strong>in</strong>vestment required <strong>in</strong> converters<br />

and cable for every <strong>in</strong>vestment. The few larger steps<br />

for Sweden-Latvia and Ireland-France reflect the greater<br />

amounts of subsea cable required for longer <strong>in</strong>terconnections.<br />

The <strong>in</strong>vestment cost curve beg<strong>in</strong>s to plateau<br />

for the hub-to-hub cases implemented, as these require<br />

only an <strong>in</strong>vestment <strong>in</strong> extra subsea cable and utilise the<br />

FIGURE 4.24: dIREcT dESIGN - cUMUlATIvE cAPEX INvESTMENT cOSTS (blUE, lEFT) ANd SYSTEM GENERATION cOSTS (REd, RIGhT) [€ bN]<br />

Cumulative <strong>in</strong>vestment<br />

cost (blue) (€bn)<br />

8<br />

7<br />

6<br />

5<br />

4<br />

3<br />

2<br />

1<br />

0<br />

Base case<br />

SE-DE<br />

FI-EE<br />

SE-PL<br />

SE-DK<br />

SE-LV<br />

GB-FR<br />

SE-DE<br />

Cumulative <strong>in</strong>vestment costs<br />

GB-BE<br />

Direct <strong>in</strong>terconnections<br />

Hub-to-hub and Tee-<strong>in</strong> Mesh<br />

Omitted as not bene�cial. Shown to compare with direct design<br />

GB-FR<br />

SE-PL<br />

SE-DK<br />

IE-FR<br />

IE-GB<br />

GB-BE<br />

NO-NL<br />

Annual system generation costs<br />

SE-DK<br />

System generation<br />

cost (red) (€bn)<br />

NL-GB<br />

GB-DE<br />

Mesh<br />

100,5<br />

100,0<br />

99,5<br />

99,0<br />

98,5<br />

98,0<br />

63

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!