10.12.2012 Views

Handbook of Electrical Installation Practice - BeKnowledge

Handbook of Electrical Installation Practice - BeKnowledge

Handbook of Electrical Installation Practice - BeKnowledge

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

36 <strong>Handbook</strong> <strong>of</strong> <strong>Electrical</strong> <strong>Installation</strong> <strong>Practice</strong><br />

served. If the load demand is <strong>of</strong> sufficient magnitude, the consumer will find it practical<br />

and economic to take the supply at high voltage (h.v.). For the purpose <strong>of</strong> this<br />

handbook the upper limit is 11kV, although for very large complexes the intake<br />

might be at 33kV or even higher. It is the consumer’s responsibility to control and<br />

distribute the electricity around his site or premises to suit his own requirements.<br />

The main substation serving a network incorporates the supply intake point,<br />

but there may be other substations located at strategic areas in a large complex<br />

and connected to the main substation by a cable network. The manner in which<br />

this interlinking occurs depends on a number <strong>of</strong> factors and is fully discussed in<br />

Chapter 3.<br />

If the supply is taken at 11kV the main substation will include 11kV switchgear<br />

which may serve other substations at 11kV throughout the site. Stepdown transformers<br />

at the site substations provide power at the consumer voltage. For very<br />

small installations the intake may be a single cable providing a three-phase 400/<br />

230V supply to a switch and fuse board. In between are a variety <strong>of</strong> arrangements.<br />

Depending on the importance <strong>of</strong> the load served, there may be a standby generator(s)<br />

linked to the system and arranged to supply essential loads. Some<br />

manufacturing complexes may generate their own power, particularly where the<br />

generation <strong>of</strong> process steam is related to the electrical requirements. Generally<br />

speaking it is uneconomic to rely on self-generation totally because <strong>of</strong> the cost <strong>of</strong><br />

standby generators. Such sites would normally have a standby supply from the mains<br />

network. In that case synchronising is required in the main substation to allow<br />

paralleling <strong>of</strong> the two systems. Alternatively, the two systems are interlocked to<br />

prevent accidental paralleling. Particular attention would be required to limit the<br />

fault power, the effects <strong>of</strong> reverse power and for discrimination under fault conditions.<br />

There would also be a problem in sharing responsibility. The magnitude and<br />

the importance <strong>of</strong> the load dictate the nature <strong>of</strong> the supply and distribution network<br />

and hence the design <strong>of</strong> the substations and control facilities.<br />

Two points should be noted in respect <strong>of</strong> the demarcation between the supply<br />

authority and the consumer’s equipment. The first is that there may be annual rates<br />

levied on any transformer between the supply point and the consumer’s distribution<br />

system. Secondly, while the supply authority may provide, install, operate and<br />

own all <strong>of</strong> the equipment up to the point <strong>of</strong> supply, it may require the consumer to<br />

make a contribution to the capital cost <strong>of</strong> making this supply available and will in<br />

many cases ask for a site on the consumer’s premises to house it. It is common but<br />

not invariable for the supply authority to insist on a separate room or locked-<strong>of</strong>f<br />

area for its apparatus.<br />

There is therefore a wide variety <strong>of</strong> possible arrangements. The client’s contractor<br />

is normally responsible for ensuring that the whole scheme is installed in a safe<br />

and secure manner with due regard to all health and safety regulations in accordance<br />

with the Health and Safety at Work etc. Act and in compliance with the<br />

client’s specifications. The site engineer therefore has a heavy responsibility. If a<br />

design drawing shows an unsafe arrangement or one which conflicts with good practice,<br />

he must draw this to the attention <strong>of</strong> his employer so that it may be remedied.<br />

<strong>Electrical</strong> power systems can cause death and injury if not properly installed. The<br />

local authority and the fire authority inspect any new properties to check that they<br />

are safe. If they are not, the remedial work could be expensive, especially if it

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!