UNDERCARRIAGE / Upper And Lower Roller

Installation

1. Place the lower roller on the track link so that the

roller mounting bolt holes on the collar align with

those on the track frame.

Lower the track frame until the clearance between

the track frame and the lower roller is very close.

W105-03-06-012

2. Install the lower roller to the track frame with bolts

(1).

: 22 mm

: 245 N⋅m (25 kgf⋅m, 180 Ibf⋅ft)

1

3. Tighten the track adjuster valve (2). Jack up the

track being adjusted for its sag. Then turn the

track slightly towards the reversed direction.

Supply the grease via grease fitting (3) to adjust

the track tension.

2

M102-07-063

Track sag specifications (A): 210 to 245 mm

(8.3 to 9.6 in)

: 24 mm

: 147 N⋅m (15 kgf⋅m, 108 Ibf f⋅ft)