Resolution Fact Sheet (Continued)<br />

A separate project entitled Newark Avenue Roadway Improvements, Phase 3 Additional<br />

Side Street Work J.C. Project No. 09-006X wil continue the above noted streetscape<br />

improvements on side streets along Newark Avenue due to in eligible Federal funding under<br />

the ARRA ~rant.<br />

5. Anticipated Benefits to the Community:<br />

The Newark Avenue Roadway project wil improved pedestrian and vehicular traffc flow and<br />

safety, decrease air pollution, improve aesthetics and encourage shopping, fine dining,<br />

nightlife, culture venues for the community and future redevelopment.<br />

6. Cost of Proposed Program, etc. (Indicate the dollar amount of <strong>City</strong>, State and Federal<br />

Funds to be used, as well as match and in-kind contributions):<br />

Funds for this project are being provided by the American Recovery and Reinvestment Act<br />

(ARRA) and Newark Avenue <strong>City</strong> Capital Funds.<br />

FINAL PROJECT FUNDING SUMMARY<br />

, Funding Source Account No. Amount<br />

AR Grant 02-213-40-099-314<br />

Newark Avenue Capital 04-215-55-880-990<br />

Total Base Bid Amount + Alternate A<br />

Newark Avenue Capital 04-215-55-880-990<br />

20 % Contingency<br />

Total Encumbrance<br />

$ 2,644,817.80<br />

$ 524,250.00<br />

$ 3,169,067.80<br />

$ 633,813.56<br />

$ 3,802,881.36<br />

Funding Sources for 09-006 and 09-006X Projects<br />

$4,311,708.00 American Recovery and Reinvestment Act Grant for Construction<br />

$1,020,000.00 NJDOT Local Aid ATP 2010 Grant<br />

$2,422,000.00 Newcirk Avenue Streetscape Capital Account<br />

$ 154,600.00 TYLI Professional Engineering Services Contract for Design<br />

(<strong>City</strong> Funds: Operating Budget)<br />

Construction Costs<br />

Project No. 09-006<br />

, Project No. 09-006x<br />

Total<br />

$3,169,067.80 + 20% Contingency $633,813.56 = $3,802,881.36<br />

$1! 185,761.52 +20% Contingency $237,152.30 = $1,422,913.82<br />

$4,354,829.32 Total Encumbered $5,225,795.18<br />

7. Date Proposed Program or Project wil Commence:<br />

Construction to start in September 2010<br />

8. Anticipated Completion Date:<br />

Time for completion is 300 Calendar Days. Construction to be completed in the Summer of<br />

2011.<br />

9. Person Responsible for Coordinating Proposed Program, Project, etc.:<br />

John Mucha, P.E.<br />

NAME<br />

10. Additional Comments:<br />

(201) 547-4757<br />

TELEPHONE EVENING<br />

~.<br />

J 7l/;o Dafe

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!