AGENDA ITEM EXECUTIVE SUMMARY<br />

Agenda Item# 13-205<br />

Resolution Name Approving Phase Construction Engineering Engineeng Serves Agreement with GANW<br />

*­ 1: ><br />

Corporation for Plank Road Realignment, <strong>Kane</strong> <strong>County</strong> Section No. URS FP<br />

W4 16<br />

El Ordinance<br />

Presenter/Sponsor: Steve Coffi nbargar - Assistant Director of Transportation<br />

Budget Information: Was this item budgeted? j Yes j No N/A<br />

If not budgeted,<br />

explain funding<br />

source<br />

Appropriation Amount: $392,107.80<br />

SUMMARY: The Plank Road Realignment and Burlington Road Intersection Improvement will realign Plank Road with the intersection of<br />

Burlington Road while addressing drainage and other infrastructure elements. The improvement will involve the demolition<br />

and reconstruction of portions of Burlington and Plank Roads with construction of a new east leg of Plank Road to create the<br />

new intersection alignment.<br />

Staff completed the consultant selection process using current QBS Procedures. The QBS Process entails notification of<br />

thel22 consulting firms within KDOTQBS Database by email of the <strong>County</strong>'s need for professional services. 25 consulting<br />

firms responded and submitted a Statement of Interest. Three pre-qualified consulting firms were short-listed and<br />

requested to submit a proposal. Staff conducted face to face interviews, which along with the proposal, were used to<br />

develop an overall score for each firm. The overall score of each firm is as follows: URS -90, exp US Serv -83, H W Lochner -<br />

75.<br />

URS Corporation was selected and a contract was negotiated to provide Phase III Engineering Services for a not to exceed<br />

amount of $392,107.80.<br />

Attachments: Resolution, Engineering Agreement<br />

Detailed information available from:<br />

Resolution/Ordinance Tracking:<br />

Staff Name: Steve Coffinba rga r, AssistantDirector Phone: 1(630) 406-7170 I<br />

Assigned Committee: Transportation Passed Sentto: Executive on: 05/15/2013<br />

If Other, specify:<br />

Committee Remarks:<br />

Next Committee: Executive Passed Sent to: <strong>County</strong> Board on: 06/05/2013<br />

If Other, specify:<br />

Committee Remarks:<br />

Next Committee:<br />

Committee Remarks:<br />

<strong>County</strong> Board Date: 06/11/2013<br />