Capital Project Funds<br />
Capital Program<br />
Major Projects<br />
Public Works Weatherization Project:<br />
This repair and renovation project was completed in February <strong>2008</strong> and the building was<br />
reoccupied on March 1 st . Numerous original structural and construction deficiencies were<br />
discovered and corrected under contract amendment during this project and the building is now<br />
ready to serve the county for the long term. The project was completed within the budget and<br />
on time by the local <strong>Kitsap</strong> <strong>County</strong> firms of Fischer General Contracting, Inc. and Rice Fergus<br />
Miller Architecture and Planning.<br />
The contract award amount for Fischer General Contracting was $2,554,250 and amended to a<br />
final construction cost of $2,725,656.<br />
Coroner Facility:<br />
The Coroner’s current facility is divided with the morgue located in the basement of an old<br />
house and the administrative offices located in a county-owned building south of the current<br />
Port Orchard campus. The current morgue is clearly substandard and poorly equipped to handle<br />
any event of significant proportions. In order to serve the needs of the <strong>County</strong> now and into the<br />
future, the <strong>County</strong> will construct a modern facility located on the Readiness Center campus in<br />
Bremerton. This will locate the facility next to the new Central Communications building which is<br />
centrally located within the <strong>County</strong>. The building is designed by Rice Fergus Miller Architects in<br />
Bremerton. The project is to be accomplished under a tight budget and has been valueengineered<br />
to appropriate minimum levels. The design was complete in spring of 2007 and<br />
construction should be underway in early <strong>2008</strong>. The current budget for this project is $3.8<br />
million.<br />
Courthouse Renovation:<br />
The current scope of work for the existing Courthouse is to renovate the interior of the building<br />
in order to render it functional for the short term, while the <strong>County</strong> developments a long term<br />
plan for a permanent Law and Justice facility.<br />
Other Capital Projects:<br />
• Model Toxic Control Act Fund established to account for financing for landfill closures<br />
on Bainbridge Island, the Norseland mobile home park and Hansville as required by the<br />
State of Washington Model Toxic Control Act.<br />
• Juvenile Services Facility Fund established to account for the construction of a new and<br />
expanded Juvenile Services Facility.<br />
• 1998 LTGO Bond Project Fund established to account for technology projects.<br />
• 1999 LTGO Bond Project Fund established to account for acquisition of open space<br />
land.<br />
187