with other structures, vehicular traffic, existing utilities, and locations vulnerable to damage or<br />

vandalism. See DSG section 5.6.3.12.<br />

5.8.3.12 Line Valves<br />

Each transmission main project should examine the proposed route for the best location of<br />

isolation line valves. Consideration should be given to future operational issues such as draining<br />

the pipeline and isolating a mainline break. SPU recommends placing isolation valves at least<br />

every 2,000 ft and at every intertie location. All line valves should be installed within a vault per<br />

the standard line valve vault detail in the DSG (see Figure 5-5 in section 5.6.3.11).<br />

5.8.4 Seismic Design<br />

This section describes seismic requirements for water system design.<br />

5.8.4.1 Critical Needs Assessment<br />

The purpose of a critical needs assessment is to establish design requirements to provide for the<br />

highest level achievable for continuity of service, i.e. for the transmission pipeline to function<br />

within its design limits with as little service interruption as possible. A critical needs assessment<br />

of the proposed new or refurbished transmission main and associated facilities should be<br />

completed as part of the basis of design. From the critical needs assessment, design criteria<br />

should be clearly established for the following:<br />

Design operational life of the transmission main.<br />

Maximum length of time that the transmission main can be out of service for repairs<br />

or maintenance without negatively affecting the water demand requirements.<br />

Identify seasonal considerations that affect the length of time the main can be out of<br />

service.<br />

Redundancy of critical components or functions, such as line isolation valves.<br />

Accessibility for the transport of repair and maintenance equipment.<br />

Access to the interior of pipes, vaults, and other structures for inspections and<br />

repairs.<br />

Impacts from geologic events (landslides, erosion) and seismic events (ground<br />

movement), including:<br />

Foundation and backfill requirements<br />

Drainage and control of or protection against groundwater<br />

Allowable pipe movement<br />

Allowable joint leakage (if any)<br />

Need for and location of seismic valves<br />

5.8.4.2 Seismic Joints and Connections for Pipe Movement<br />

This section describes potential design issues when SPU water pipes must cross settlement<br />

prone areas, faults, liquefaction zones, slides, or where two types of pipe with different restraint<br />

characteristics must be connected. In both cases, design must allow pipe movement.<br />

5-44 SPU Design Standards and Guidelines