14.04.2014 Views

2013 Water System Plan, Volume II - Seattle City Clerk's Office - City ...

2013 Water System Plan, Volume II - Seattle City Clerk's Office - City ...

2013 Water System Plan, Volume II - Seattle City Clerk's Office - City ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

ange of available sizes, steel pipe size may need to be reduced in the<br />

immediate vicinity of the ball joints. See Virtual Vault plan set 785-38 for an<br />

example of an 89-inch OD steel pipe crossing a slide plane with a 48-inch double<br />

ball expansion joint.<br />

Where fault crossings/slide planes are encountered, a double ball expansion joint should be<br />

installed right at the fault crossing as shown in Virtual Vault plan set 785-38. If this is not<br />

possible, the thickest pipe wall and strongest steel should be used, with some flexibility built in<br />

elsewhere if possible.<br />

Design considerations such as predicted ground movement, installation cost, cost of failure, and<br />

reliability must be analyzed. It may be cheaper to install an inexpensive pipe system and replace<br />

it every 10 years than to install a system that will last 100 years. Some SPU pipelines are<br />

extremely critical and must be designed to withstand the largest expected ground movement.<br />

5.8.4.3 Seismically Actuated Valves<br />

Seismically actuated valves automatically close during an earthquake to prevent the<br />

uncontrolled drainage from water storage tanks due to broken downstream pipelines. Many<br />

factors must be determined for each valve installation: sensitivity, speed to close, battery life<br />

requirements, power availability, and SCADA.<br />

The seismic actuator must be properly matched to the valve it protects.<br />

All valves must have a manual operator for emergency operation.<br />

5.8.5 Inter-Connection of Parallel Mains<br />

In some cases, pipelines may be installed parallel, or a new line may be installed near an existing<br />

main. The design engineer should consider whether a connection between the two pipelines is<br />

possible and beneficial. A primary reason to consider the interconnection is draining of the<br />

pipelines. Typically, when a pipeline is drained, millions of gallons of water are wasted. Pumping<br />

from pipeline to pipeline allows for much faster draining than can normally be achieved by<br />

draining to the water system. If parallel or nearby pipelines are interconnected, water from the<br />

pipeline to be drained can be pumped into the other pipeline, thus not wasting water.<br />

The interconnection between mains will likely require room for a pump. If possible, route an<br />

interconnection line from each pipeline into a single vault, leaving a gap for a pump and the final<br />

connecting piping. The size of the interconnection should be based on flow calculations and an<br />

acceptable amount of time to drain the line. A good location for an intertie is at the blow-off.<br />

5.8.6 Rehabilitation of Existing Mains<br />

See DSG section 5.6.5.<br />

5.8.7 Emergency Pump Connections<br />

See DSG section 5.6.6.<br />

5.8.8 SCADA<br />

See DSG section 5.6.7.<br />

5-46 SPU Design Standards and Guidelines

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!