SPU requires a pre-installation taste and odor testing of water pipe (Standard<br />

Specification 7-11.2[2]) of non-approved pipe sources. Request a current list from the<br />

SPU <strong>Water</strong> Quality group.<br />

B. Pipe Installation and Repairs<br />

Controlling water and soil from entering pipes is a critical factor for achieving sanitary<br />

conditions in water mains. See Standard Specifications for sanitary control practices for<br />

water main construction and repairs:<br />

Section 7-11.3(2)A Handling of Pipe – General<br />

Section 7-11.3(5) Cleaning and Assembling Joints<br />

5.10.3.4 Post-Construction or Repair Startup and Acceptance<br />

A. Acceptance<br />

After water main construction or repair, the following requirements must be met before<br />

SPU will accept the connection to the water system and place it into service:<br />

Hydraulic and structural integrity, as demonstrated by hydrostatic pressure<br />

testing<br />

Sanitary conditions, as provided by flushing, disinfection, and verified by water<br />

quality testing<br />

B. Hydrostatic Pressure Testing<br />

<strong>Water</strong> mains and appurtenances, including extensions from existing water mains greater<br />

than 18 feet, hydrants, and hydrant runs must meet the requirements of Standard<br />

Specification 7-11.3(11).<br />

C. Cleaning and Flushing<br />

After a water main installation has passed the hydrostatic pressure tests, cleaning and<br />

flushing must be completed per the requirements of Standard Specification 7-11.3(12)B.<br />

D. Disinfection<br />

The following Standard Specifications address water main disinfection procedures:<br />

Section 7-11.3(12)C<br />

Section 7-11.3(12)D<br />

Section 7-11.3(12)E<br />

Section 7-11.3(12)F<br />

Section 7-11.3(12)G<br />

Section 7-11.3(12)H<br />

Section 7-11.3(12)K<br />

Required Contact Time<br />

Form of Applied Chlorine<br />

Chlorine Dosage<br />

Point of Application for Liquid/Gas Disinfection<br />

Backflow Prevention Requirement<br />

Rate of Application<br />

E. <strong>Water</strong> Quality Testing and Criteria<br />

Disinfection of Connections to Existing <strong>Water</strong> <strong>System</strong>s<br />

5-68 SPU Design Standards and Guidelines