SPU requires a pre-installation taste and odor testing of water pipe (Standard<br />
Specification 7-11.2[2]) of non-approved pipe sources. Request a current list from the<br />
SPU <strong>Water</strong> Quality group.<br />
B. Pipe Installation and Repairs<br />
Controlling water and soil from entering pipes is a critical factor for achieving sanitary<br />
conditions in water mains. See Standard Specifications for sanitary control practices for<br />
water main construction and repairs:<br />
Section 7-11.3(2)A Handling of Pipe – General<br />
Section 7-11.3(5) Cleaning and Assembling Joints<br />
5.10.3.4 Post-Construction or Repair Startup and Acceptance<br />
A. Acceptance<br />
After water main construction or repair, the following requirements must be met before<br />
SPU will accept the connection to the water system and place it into service:<br />
Hydraulic and structural integrity, as demonstrated by hydrostatic pressure<br />
testing<br />
Sanitary conditions, as provided by flushing, disinfection, and verified by water<br />
quality testing<br />
B. Hydrostatic Pressure Testing<br />
<strong>Water</strong> mains and appurtenances, including extensions from existing water mains greater<br />
than 18 feet, hydrants, and hydrant runs must meet the requirements of Standard<br />
Specification 7-11.3(11).<br />
C. Cleaning and Flushing<br />
After a water main installation has passed the hydrostatic pressure tests, cleaning and<br />
flushing must be completed per the requirements of Standard Specification 7-11.3(12)B.<br />
D. Disinfection<br />
The following Standard Specifications address water main disinfection procedures:<br />
Section 7-11.3(12)C<br />
Section 7-11.3(12)D<br />
Section 7-11.3(12)E<br />
Section 7-11.3(12)F<br />
Section 7-11.3(12)G<br />
Section 7-11.3(12)H<br />
Section 7-11.3(12)K<br />
Required Contact Time<br />
Form of Applied Chlorine<br />
Chlorine Dosage<br />
Point of Application for Liquid/Gas Disinfection<br />
Backflow Prevention Requirement<br />
Rate of Application<br />
E. <strong>Water</strong> Quality Testing and Criteria<br />
Disinfection of Connections to Existing <strong>Water</strong> <strong>System</strong>s<br />
5-68 SPU Design Standards and Guidelines