At 10% discount rate, the levelised costs <strong>of</strong> wind generated electricity are significantly higher than at<br />
5% discount rate owing to the predominant share <strong>of</strong> investment in the total. They range between 45 and<br />
more than 140 USD/MWh.<br />
Hydro power plants<br />
Data were provided for eight hydro power plants in six countries. 1 The specific overnight construction<br />
costs per unit <strong>of</strong> capacity reported (see Figure 4.5) vary widely, as may be expected, because hydro power<br />
plant construction costs depend mainly on site specific characteristics. The expense schedules reported for<br />
hydro power plants correspond to construction periods ranging from 1 to 5 years but in most cases most<br />
<strong>of</strong> the expenses are incurred in less than 3 years.<br />
Figure 4.5 – Specific overnight construction costs <strong>of</strong> hydro power plants (USD/kWe)<br />
USD/kWe<br />
7 000<br />
6 000<br />
5 000<br />
4 000<br />
3 000<br />
2 000<br />
1 000<br />
0<br />
AUT-H1<br />
AUT-H2<br />
CZE-H<br />
DEU-H<br />
GRC-H1<br />
GRC-H2<br />
SVK-H<br />
JPN-H<br />
The hydro power plants considered in the study are small or very small units, except the dam in Greece<br />
(GRC-H2) which has a total capacity <strong>of</strong> some 120 MWe. The very high specific construction costs<br />
reported for most <strong>of</strong> the hydro power plants considered in the study likely result from their small sizes,<br />
although in Austria the specific construction costs reported are lower for the smaller unit.<br />
The specific annual O&M costs reported for hydro power plants are given in Table 4.2. Similarly to the<br />
construction costs they vary widely from plant to plant, even in the same country owing to the site specific<br />
characteristics <strong>of</strong> hydro power. Except in the Czech Republic, O&M costs are projected to remain<br />
constant during the lifetime <strong>of</strong> the plant.<br />
Table 4.2 – Specific annual O&M costs (per kWe) for hydro power plants in 2010<br />
AUT-H1 AUT-H2 CZE-H a DEU-H GRC-H1 GRC-H2 SVK-H JPN-H<br />
NCU 44.82 19.18 1 389 58.80 78.80 3.00 1 577 14 837<br />
USD 39.18 21.94 50.42 67.27 90.15 3.43 43.37 124.63<br />
€ 44.82 19.18 44.07 58.80 78.80 3.00 37.91 108.94<br />
a. Increasing over time.<br />
1. Also, Bulgaria and the Republic <strong>of</strong> South Africa provided information on pumped storage facilities for which generation<br />
costs cannot be estimated with the generic assumptions adopted within the study.<br />