Coal & Allied – Hunter Valley Operations<br />

Groundwater Monitoring EC Results for Carrington Piezometers<br />

The highest average EC level was CGW51A with 11,185μS/cm, the lowest average EC level was CGW6 with<br />

2,050μS/cm (Figure 46). These results are consistent with historical data. Please refer to ‘Interpretation of<br />

Groundwater Monitoring Results for Carrington Piezometers’ below. In addition a review of groundwater<br />

related impacts has been undertaken for the Carrington Pit area. The report “Carrington Extended – Review<br />

of Mining Related Impacts on the Paleochannel Groundwater System” is attached in Appendix 10.<br />

13,000<br />

Carrington Groundwater EC Trends<br />

12,000<br />

11,000<br />

10,000<br />

Electrical Conductivity (uS/cm)<br />

9,000<br />

8,000<br />

7,000<br />

6,000<br />

5,000<br />

4,000<br />

3,000<br />

2,000<br />

1,000<br />

0<br />

Jan 09<br />

Feb 09 Mar 09<br />

Apr 09<br />

May 09<br />

Jun 09<br />

Jul 09 Aug 09<br />

Date<br />

Sep 09<br />

Oct 09<br />

Nov 09<br />

Dec 09<br />

Jan 10<br />

CGW39 CGW45 CGW46 CGW49 CGW51A CGW52 CGW52A CGW54A CGW6<br />

Figure 46: Carrington Groundwater EC Trends<br />

Groundwater Monitoring SWL Results for Carrington Piezometers<br />

The standing water level results are shown in Figure 47. Piezometers into the alluvium are those with depths<br />

to water of less than 15m. These results are consistent with historical data. Please refer to ‘Interpretation of<br />

Groundwater Monitoring Results for Carrington Piezometers’ below. In addition a review of groundwater<br />

related impacts has been undertaken for the Carrington Pit. The report “Carrington Extended – Review of<br />

Mining Related Impacts on the Paleochannel Groundwater System” is attached in Appendix 10.<br />

AEMR <strong>2009</strong> 97