District Watershed <strong>Development</strong> Unit - Jamnagar<br />
Table No, 41.5, Cost Estimation <strong>of</strong> Farm pond No.1<br />
Sr. No. Description Unit Quantity Rate (Rs.) Amount<br />
1 General Work<br />
Clearing bushes / Dag Belling 2.5 to 5.00 cm deep Mt 100 20.00 2000<br />
2 Earth Work<br />
Construction <strong>of</strong> earthen bund (dry <strong>of</strong> moist) excavation and laying in 15 cm layer, breaking<br />
160<br />
<strong>of</strong> clods, separating leaves and small stones, dressing and compaction with sheep foot roller<br />
or a) ordinary hand rammer, soil uptp 1.5 meter lift and 50 meter lead.<br />
Cum 160 41.00 6560<br />
b) hard soil Cum 160 96.00 15360<br />
Sub Total 6560<br />
Contingency (3 %) 196.80<br />
Supervision Charges (1.5 %] 98.40<br />
Sub Total 6855.52<br />
Grand Total<br />
Table No, 41.6, Cost <strong>of</strong> Farm pond in Village Wise:-<br />
(Rs.)<br />
Say 6900/-<br />
Sr No. Village Name Nos. Of Pond Cost<br />
1 Patan 7 56000<br />
2 Paradava 5 40000<br />
3 Amrapar 10 80000<br />
4 Malavada 3 24000<br />
Total 25 200000/-<br />
Plains or Flat level:<br />
<strong>Detailed</strong> <strong>Project</strong> <strong>Report</strong> – IWMP-1 (Patan )