Appendix 5 - Completed, Deleted, and Delayed Projects<br />
Delayed Projects from the Previous 2009/12 <strong>MTIP</strong><br />
County Lead Agency Project ID Title Description Completion Year Total Cost<br />
City of Folsom Dept of<br />
Sacramento Public Works SAC22060 East Natoma Street Widening<br />
City of Folsom Dept of<br />
Sacramento Public Works SAC24328 Scott Road Widening<br />
City of Folsom Dept of<br />
Sacramento Public Works SAC19890 US 50 at Empire Ranch Road<br />
In Folsom, East Natoma St from Fargo Way to Folsom Lake Crossing:<br />
widen from 2 to 4 lanes and construct bicycle trail undercrossing. STREET<br />
NAME: East Natoma Street Widening 2020 $3,150,000<br />
Widen existing Scott Road from 2 to 6 lanes between US 50 and White<br />
Rock Road 2017 $16,000,000<br />
US 50 at Empire Ranch Road: Construct 4 lane interchange with US 50 at<br />
Empire Ranch Road (formerly Russell Ranch Road). HPP #337 2030 $38,552,000<br />
Sacramento<br />
City of Folsom Dept of<br />
Public Works SAC24463 US 50 at Scott Road<br />
Ramp modifications and overpass widening for US 50/East Bidwell/Scott<br />
Road Interchange to improve access to development south of US 50. 2015 $3,180,000<br />
Sacramento City of Rancho Cordova SAC24375 Americanos Road, Phase I New 4 lane roadway from Chrysanthy to North of Douglas Road. (Phase 1) 2015 $2,925,000<br />
Sacramento City of Rancho Cordova SAC24193<br />
Grant Line Road - Expressway<br />
Phase I<br />
Grant Line Road: Widen existing roadway to four lanes and complete<br />
remaining sections of four lane Expressway from Jackson Highway to<br />
White Rock Road including intersection improvements at Jaeger Road,<br />
Keifer Blvd, International Drive and Jackson Highway. (Phase 1) 2022 $86,200,800<br />
Sacramento City of Rancho Cordova SAC24374 Kiefer Boulevard, Phase 2<br />
Complete widening and extend Kiefer Blvd. as a new four lane roadway<br />
from Rancho Cordova Parkway (Jaeger Road) to Americanos Road<br />
including intersection improvements at Americanos and Grant Line.<br />
(Phase 2 - CP09-2074) 2016 $7,451,000<br />
Sacramento City of Rancho Cordova SAC24239 Purchase or Lease 23 Shuttles<br />
Replace contracted shuttle fleet with city owned or leased fleet, including<br />
three back-up vehicles (23 shuttles total) 2022 $5,750,000<br />
Sacramento City of Rancho Cordova<br />
SAC22980<br />
Rancho Cordova Parkway -<br />
Phase 1<br />
Sacramento City of Rancho Cordova SAC24181 Rio Del Oro Pkwy<br />
Sacramento City of Rancho Cordova SAC24208 Sun Center Drive<br />
Sacramento City of Rancho Cordova SAC20240<br />
Zinfandel Road Extension &<br />
Folsom South Canal Bridge<br />
City of Sacramento Dept<br />
Sacramento of Transportation SAC18460 East Commerce Way<br />
City of Sacramento Dept<br />
Sacramento of Transportation SAC18510 Elkhorn Boulevard<br />
City of Sacramento Dept<br />
Sacramento of Transportation SAC18560 Natomas Crossing Drive<br />
Phase 1: In Rancho Cordova, Douglas Road to White Rock Road,<br />
construct Rancho Cordova Parkway as a six lane roadway including<br />
intersection improvements at Villagio and White Rock Road. 2020 $19,839,000<br />
Rio Del Oro Parkway: New 4 lane roadway from Sunrise Boulevard to<br />
Rancho Cordova Parkway and a new 2 lane road from Rancho Cordova<br />
Parkway to White Rock Road including intersection improvements at<br />
Sunrise Blvd., Rancho Cordova Parkway, Americanos Blvd., and White<br />
Rock Road (CP09-2070) 2018 $12,795,000<br />
New two lane roadway from Folsom South Canal to White Rock Road<br />
including intersection improvements from Mercantile to White Rock Road<br />
including bridge over Folsom South Canal. 2020 $13,670,000<br />
Extend Zinfandel Drive as a six lane roadway from Southern boundary of<br />
the Villages of Zinfandel to Douglas Road and widen Douglas Road to 6<br />
lanes from Zinfandel to Sunrise Boulevard including bridge over Folsom<br />
South Canal and intersection improvements at Eagles Nest. (This is Phase<br />
3. See SAC24473 and SAC24467) 2015 $10,500,000<br />
In Sacramento, East Commerce Way from Club Center Drive to Del Paso<br />
Rd, extend as a 6-lane facility. 2020 $8,<strong>14</strong>2,225<br />
In Sacramento, Elkhorn Boulevard from SR 99 to east city limits: widen<br />
from 2 to 6 lanes. 2020 $7,073,566<br />
In City of Sacramento, build new Natomas Crossing Drive as 2 lane road<br />
from Duckhorn Drive to El Centro Rd. 2020 $4,340,715<br />
<strong>2011</strong> <strong>MTIP</strong> - Page 358 of 423<br />
Delayed Projects: Page 35 of 39