97 Dy. Executive Engineer<br />
GENERAL SPECIFICATION FOR WATERPROOFING<br />
1. The work of waterproofing described in the following items shall be carried out by the<br />
contractor only through a renowned specialist water proofing agency using cement<br />
waterproofing compounds, as approved in writing by the Engineer-in-charge.<br />
2. The contractor shall give before execution, detailed specifications for each item of work<br />
waterproofing to be executed according to the specifications of the specialist agency he<br />
proposes to employ for approval. The work shall not be started unless approval in writing is<br />
given by the Engineer-in-charge to the said specifications.<br />
3. The contractor shall give a Guarantee Bond on requisite stamp paper for a minimum period of<br />
ten Years for all the items of waterproofing done. During the guarantee period the contractor<br />
shall entirely be responsible to rectify any defect at his own cost to maintain the work in<br />
waterproof condition. The waterproofing contractor shall also have to make good all the<br />
surroundings disturbed by him during the rectification work at his own cost. The form of<br />
written guarantee shall be all legal stamped agreements acceptable to the Government. The<br />
guarantee shall be given within in one month from the date of completion of waterproofing<br />
treatment but any delay in furnishing the guarantee shall not relieve the contractor from the<br />
implications of this clause.<br />
4. 10% (ten Present) of the cost of the waterproofing work executed shall be retained as<br />
"Retention Money" for a period of 10 years covering the guarantee. And the same shall be<br />
released only after satisfactory performance of the treatment during guarantee period of 10<br />
years. The amount may be converted into any approved interest bearing security (for ten<br />
years after completion of defect liability period), in the name of Executive Engineer, Public<br />
Works Division, Jawhar on receipt of such written request from the contractor.<br />
5. The waterproofing agency as approved by Engineer-in-charge shall provide and install at his<br />
own cost the following for his own use and remove the same after completion of the work.<br />
I) Two pumps electrical/diesel operated for watering and curing at any level in the<br />
building. Curing shall be carried out for a minimum period of 14 days.<br />
II) Temporary mild steel water storage tanks.<br />
III) temporary galvanised iron pipings and fittings for water line.<br />
IV) Flexible hose lengths.<br />
V) Cement godown, site office.<br />
6. Injections to reinforced cement concrete slab, wherever required, have to be undertaken by<br />
the contractor free of cost.<br />
7. Before starting the waterproofing work, the surface receiving the treatment shall be cleaned<br />
properly.<br />
8. The item of waterproofing as given in the Schedule 'B' applies for work in any portion and on<br />
any floor and at any height. The lift of materials shall not form any criteria for extra payment.<br />
9. For the reference of contractor, general guideline specifications for waterproofing are<br />
attached herein with the general specification for waterproofing.<br />
Signature of Contractor <strong>No</strong>. Of Corrections Executive Engineer