97 Dy. Executive Engineer<br />

GENERAL SPECIFICATION FOR WATERPROOFING<br />

1. The work of waterproofing described in the following items shall be carried out by the<br />

contractor only through a renowned specialist water proofing agency using cement<br />

waterproofing compounds, as approved in writing by the Engineer-in-charge.<br />

2. The contractor shall give before execution, detailed specifications for each item of work<br />

waterproofing to be executed according to the specifications of the specialist agency he<br />

proposes to employ for approval. The work shall not be started unless approval in writing is<br />

given by the Engineer-in-charge to the said specifications.<br />

3. The contractor shall give a Guarantee Bond on requisite stamp paper for a minimum period of<br />

ten Years for all the items of waterproofing done. During the guarantee period the contractor<br />

shall entirely be responsible to rectify any defect at his own cost to maintain the work in<br />

waterproof condition. The waterproofing contractor shall also have to make good all the<br />

surroundings disturbed by him during the rectification work at his own cost. The form of<br />

written guarantee shall be all legal stamped agreements acceptable to the Government. The<br />

guarantee shall be given within in one month from the date of completion of waterproofing<br />

treatment but any delay in furnishing the guarantee shall not relieve the contractor from the<br />

implications of this clause.<br />

4. 10% (ten Present) of the cost of the waterproofing work executed shall be retained as<br />

"Retention Money" for a period of 10 years covering the guarantee. And the same shall be<br />

released only after satisfactory performance of the treatment during guarantee period of 10<br />

years. The amount may be converted into any approved interest bearing security (for ten<br />

years after completion of defect liability period), in the name of Executive Engineer, Public<br />

Works Division, Jawhar on receipt of such written request from the contractor.<br />

5. The waterproofing agency as approved by Engineer-in-charge shall provide and install at his<br />

own cost the following for his own use and remove the same after completion of the work.<br />

I) Two pumps electrical/diesel operated for watering and curing at any level in the<br />

building. Curing shall be carried out for a minimum period of 14 days.<br />

II) Temporary mild steel water storage tanks.<br />

III) temporary galvanised iron pipings and fittings for water line.<br />

IV) Flexible hose lengths.<br />

V) Cement godown, site office.<br />

6. Injections to reinforced cement concrete slab, wherever required, have to be undertaken by<br />

the contractor free of cost.<br />

7. Before starting the waterproofing work, the surface receiving the treatment shall be cleaned<br />

properly.<br />

8. The item of waterproofing as given in the Schedule 'B' applies for work in any portion and on<br />

any floor and at any height. The lift of materials shall not form any criteria for extra payment.<br />

9. For the reference of contractor, general guideline specifications for waterproofing are<br />

attached herein with the general specification for waterproofing.<br />

Signature of Contractor <strong>No</strong>. Of Corrections Executive Engineer