SCHEDULE “ C ” AND SPECIFICATIONS<br />

NAME OF WORK:-<br />

Construction of Warehouse of 3000 Metric Tonne Capacity (2 <strong>No</strong>s) at Chikhale, in Taluka Dahanu, District Thane.<br />

Reference to Standard (PWD)<br />

Specification<br />

Description of Item<br />

Additional specification if any<br />

Specification<br />

Page <strong>No</strong>.<br />

<strong>No</strong>.<br />

1 2 3 4 5<br />

1 Item <strong>No</strong>. 1:- Excavation for foundation in earth, soils of all Bd.A.1 259 a) The item includes removal of stone, brick masonry of old<br />

types, sand gravel and soft murum including removing the<br />

structure, if any during excavation. b) The size viz length,,<br />

excavated materials upto a distance of 50 metres beyond the<br />

width and depth of excavation shown on drawing are<br />

building area and all lift, stacking and spreading, necessary<br />

tentative and may vary in actual execution. c) The decision<br />

dewatering unless provided elsewhere, preparing the bed for<br />

regarding strata classification will be taken by the executive<br />

foundation and required backfilling, ramming, watering,<br />

Engineer and shall be final and binding on the contractor. d)<br />

shoring and strutting etc. complete as directed.<br />

Item also included manual Dewatering, if any.<br />

Sr.<br />

<strong>No</strong>.<br />

2 Item <strong>No</strong>. 2:- Excavation for foundation in hard rock by<br />

blasting / old cement / lime masonry foundation including<br />

removing the excavated materials upto a distance of 50<br />

metres beyond the building area and all lift, stacking and<br />

spreading, necessary dewatering unless provided elsewhere,<br />

preparing the bed for foundation and required backfilling,<br />

ramming, watering, shoring and strutting etc. complete as<br />

directed.<br />

3 Item <strong>No</strong>. 3:- Providing soling using 80 millimetre size trap<br />

metal in layers of 15 centimetre each including filling voids<br />

with sand, ramming, watering etc. complete<br />

Bd.A.5 259 a) The item includes removal of stone, brick masonry of old<br />

structure, if any during excavation. b) The size viz length,,<br />

width and depth of excavation shown on drawing are<br />

tentative and may vary in actual execution. c) The decision<br />

regarding strata classification will be taken by the executive<br />

Engineer and shall be final and binding on the contractor. d)<br />

Item also included manual Dewatering, if any.<br />

Bd.A.12 264 a) The size of trap rubble should be 80mm b) The sand<br />

required to till the voids in the soling shall be dry and spread<br />

uniformly over the soling and brushed and washed to fill the<br />

interstices fully. c) The metal soling shall be laid and the<br />

voids in the metal layer shall be filled with hand rammer so<br />

as to achieve compact surface. d) The contract rate shall be<br />

for one cubic metre of the compacted layer of metal soling<br />

duly filed in the voids with sand. <strong>No</strong> extra payment shall be<br />

made for filling voids with sand.<br />

106<br />

Signature Of Contractor <strong>No</strong>. Of Corrections Executive Engineer<br />

P.W. Division, Jawhar