30 Dy. Executive Engineer<br />

4. Any person who submits a tender shall fill up the usual printed form stating at what<br />

percentage above or below the rates specified in Schedule B (Memorandum showing items of<br />

work to be carried out) he is willing to undertake the work. Only one rate or such percentage<br />

on all the Estimated rates/Schedule rates shall be stated. <strong>Tender</strong>s, which propose any<br />

alteration in the works specified in the said form of invitation to tender, or in the time allowed<br />

for carrying out the work, or which contain any other conditions will be liable for rejection. <strong>No</strong><br />

printed form of tender shall include a tender for more than one work, but if contractor wishes<br />

to tender for two or more works, he shall submit a separate tender for each work. <strong>Tender</strong> shall<br />

have the name and number of the work to which it refers written outside the envelope.<br />

5. The Superintending Engineer or his duly authorized Assistant shall open tenders in the<br />

presence of contractors who have submitted tenders or their representatives who may be<br />

present at the time, and he will enter the amounts of the several tenders in a comparative<br />

statement in a suitable form. In the event of a tender being accepted, the contractor shall for<br />

the purpose of identification, sign copies of the specifications and other documents mentioned<br />

in Rule 1. In the event of tender being rejected, the Divisional officer shall authorize the<br />

Treasury Officer concerned to refund the amount of the earnest money deposited to the<br />

contractor submitting the tender, on his giving a receipt for the return of the money.<br />

6. The officer competent to dispose of the tenders shall have the right of rejecting all or any of<br />

the tenders.<br />

7. <strong>No</strong> receipt for any payment, alleged to have been made by a contractor in regard to any<br />

matter relating to this tender or the contract, shall be valid and binding on Government unless<br />

it is signed by the Executive Engineer.<br />

8. All work shall be measured net by standard measures and according to the Rules and<br />

customs of the Public Works Department and their rates shall be without references to any<br />

local custom.<br />

9. Under no circumstances shall any contractor be entitled to claim enhanced rates for any item<br />

in this contract.<br />

10. All corrections and additions or pasted slips should be initialed.<br />

11. The measurements of work shall be taken according to the usual methods in use in the Public<br />

Works Department and no proposals to adopt alternative methods shall be accepted. The<br />

Executive Engineer’s decision as to what is “the usual method in use in the Public Works<br />

Department” shall be final.<br />

12. The tendering Contractor shall furnish a declaration alongwith the tender showing all works<br />

for which he has already entered into contract and the value of the work that remains to be<br />

executed in each case on the date of submitting the tender.<br />

13. <strong>No</strong> foreign exchange would be released by the Department for the purchase of plant and<br />

machinery required for the execution of the work contracted for.<br />

(GCD/PWD/CFM/1058/62517 OF 26.5.1959)<br />

14. The contractor shall have to construct shed for storing controlled and valuable materials<br />

brought by the contractor at work site having double locking arrangement at contractor’s cost.<br />

The materials shall then be taken for use in the presence of the Departmental person. <strong>No</strong><br />

material shall be allowed to be removed from the site of works.<br />

15. The contractors shall also give a list of machinery in their possession, which they propose to<br />

use on the work.<br />

16. Successful tenderer shall have to produce to the satisfaction of the accepting authority a valid<br />

and current license issued in his favour under the provisions of Contract Labour (Regulation<br />

and Abolition) Act, 1973 before starting the work. Failing which, acceptance of the tender<br />

shall be liable for withdrawal and earnest money shall be forfeited to the Government (refere<br />

Government of Maharashtra, Irrigation and Power Department’s letter <strong>No</strong>. Lab<br />

1076h181/(666E-17), dated 8/9/1976.)<br />

17. The contractor shall comply with the provisions of Apprentices Act,1961 and the rules and<br />

orders issued thereunder from time to time. If he fails to do so, his failure shall be breach of<br />

the contract and the Chief Engineer Superintending Engineer, may in his discretion cancel the<br />

contract. The contractor shall also be liable for any pecuniary liability arising on account of<br />

any violation by him of the provisions of the said Act.<br />

Signature of Contractor <strong>No</strong>. Of Corrections Executive Engineer