20. ANCILLARY WORK :<br />
The Contractor shall submit to Engineer-in-charge in writing the details of all ancillary works<br />
including layout and specifications to be followed for its construction. Ancillary work shall not<br />
be taken up in hand unless approved by Engineer-in-charge. The Engineer-in-charge<br />
reserves the right to suggest modifications or make complete changes in the layout and<br />
specifications proposed by the Contractor at any stage to ensure the safety on the work site.<br />
The Contractor shall carry out all such modifications to the ancillary works at his own<br />
expenses as ordered by Engineer-in-charge.<br />
21 SPECIAL CONDITIONS:<br />
21.1 The Contractor should ensure that all safety precautions are observed by their laboures,<br />
working closed to the State Highway and while closing the State Highway precautions are<br />
taken including insurance etc., for their labour at the cost of the contractor and the contractor<br />
will bear all the expenses, compensation etc. if any accident occurs to the labour etc. <strong>No</strong><br />
claim in this regard on whatsoever account shall be entertained and this decision of the<br />
Department will be final and conclusive.<br />
21.2 The Contractor shall observe the rules and regulation imposed by traffic police for smooth<br />
flow of traffic on the diversion road and shall not be entitled for claims any compensation<br />
arising thereof.<br />
21.3 In case of delay in handing over the land required for the work, due to unforeseen cause, the<br />
Contractor shall not be entitled for any compensation what-so-ever form the Government on<br />
ground that the machinery or labour was idle for certain period. Contractor may, however<br />
apply for extension of time limit which may be granted on the merit of the case.<br />
22. REJECTION OF MATERIALS NOT CONFORMING TO SPECIFICATIONS:<br />
Any stock or batch of material(s) of which sample(s) does not conform to the prescribed test<br />
and quality, shall be rejected by the Engineer or his representative and such materials shall<br />
be removed from site by the Contractor at his own cost. Such rejected materials shall not be<br />
made acceptable by any modifications. Materials not corresponding in character and Quality<br />
with approved samples will be rejected by the Engineer or his representative and shall be<br />
removed from site at the Contractor’s own cost.<br />
23. INSPECTION OF OPERATIONS:<br />
The Engineer and any person authorised by him shall at all times have access to the works<br />
and to all workshops and places (including required documents) where work is being<br />
prepared or from where materials, manufactured articles or machinery are being obtained for<br />
the works and the Contractor shall afford every facility for & every assistance in or in obtaining<br />
the right to such access.<br />
24. FIELD LABORATORY:<br />
The Contractor shall arrange to provide a well-furnished and fully equipped field laboratory<br />
which shall be manned by adequately qualified technical staff. The laboratory shall preferably<br />
be located adjacent to the plant site and shall be provided with amenities like water supply,<br />
electric supply, toilet block etc. The list of equipment is enclosed on Page <strong>No</strong>.80. This shall<br />
be considered as incidental to work and no separate payment whatsoever will be made for<br />
the same.<br />
25. SUPPLY OF COLOURED RECORD PHOTOGRAPHS AND ALBUMS:<br />
The Contractor shall arrange to take dated post card size coloured photographs at various<br />
stages/facts of the work including interesting and novel features of the work as desired by the<br />
Engineer-in-charge and supply them in five copies each in separate albums of appropriate<br />
size. He shall also arrange for the Video Filming of important activities of the work during the<br />
currency of the contract and edit it to a video film of 60 to 180 minutes playing time. It shall<br />
contain narration of the various activities in English/Marathi by a competent narrator. The<br />
cassette shall be of acceptable quality and the film shall be capable of producing color<br />
pictures. This shall be considered as incidental to the work and no additional payment<br />
whatsoever will be made for the same.<br />
26. SUPPLY OF SAFETY JACKETS TO LABOURERS/SUPERVISORS/ENGINEERS<br />
As a safety measure during the execution of work all labours, construction and supervisory<br />
staff shall be provided with an orange colour jacket in fluorescent blue so as to make them<br />
starkly visible from a distance even during evening hours.<br />