59 Dy. Executive Engineer<br />

measured and recorded over again and to prevent any unauthorized tampering with the<br />

stacks. If the contractor or the piece worker fails to attend the measurements of materials<br />

after receiving the notice from the Sub Divisional Officer or his subordinate stating date and<br />

time of the intention to measure the work, the same shall be measured nevertheless and no<br />

complaint in this respect will be entertained later-on. If the contractor or piece worker fails to<br />

supply sufficient labour or the materials required at the time measurements or check<br />

measurements, after due notice has been given to him, the expenses incurred on account of<br />

employing departmental labour or material etc. shall be charged against his account.<br />

6.7 AGENT AND WORK ORDER BOOKS :-<br />

The contractor shall himself engaged an authorised all time agent on the work capable of<br />

managing and guiding the work and understand the specifications and contract condition. A<br />

qualified and experienced, Engineer shall be employed by the contractor as his agent for<br />

technical matters in case the Engineer-in-charge considers this as essential for the work and<br />

so directs contractors. He will take orders as will be given by the Executive Engineer or his<br />

representative and shall be responsible for carrying them out.<br />

This agent shall not be changed without prior intimation to the Executive Engineer and his<br />

representative on the work site. The Engineer-in-charge have the unquestionable right to ask<br />

for change in the quality and strength of contractor’s supervisory staff and to order removal<br />

from work of any of such staff. The contractor shall comply with such orders and effect<br />

replacements to the satisfaction of the Engineer-in-charge.<br />

A work order book shall be maintained on site and it shall be the property of the Government<br />

and the contractor shall promptly sign orders given therein by the Executive Engineer or his<br />

representative and his superior officers and comply with them. The compliance shall be<br />

reported by the Contractor to the Engineer in good time so that it can be checked. The blank<br />

work order with machine numbered pages will be provided by the Department free of charge<br />

for this purpose. The contractor will be allowed to copy out instructions therein from time to<br />

time.<br />

6.8 INITIAL MEASUREMENTS FOR RECORD:-<br />

Where for proper measurement of work, it is necessary to have initial set of levels or other<br />

measurements taken, the same as recorded in the authorised field book or measurement<br />

book of Government by the Engineer or his authorised representative will be signed by the<br />

Contractor who will be entitled to have a true copy of the same made at his cost. Any failure<br />

on the part of the Contractor to get such levels etc. recorded before starting the work will<br />

render him liable to accept the decision of the Engineer as to the basis of taking<br />

measurements. Like-wise the Contractor will not cover any work which will render its<br />

subsequent measurements difficult or impossible<br />

without first getting the same jointly measured by himself and the authorised representative of<br />

the Executive Engineer. The record of such measurements on the Government side will be<br />

signed by the Contractor and he will be entitled to have a true copy of the same made at his<br />

cost.<br />

6.9 HANDING OVER OF WORK :-<br />

All the works and materials before finally taken over by Government it will be the entire liability<br />

of the Contractor to guard, maintain and make good any damage of any magnitude. Interim<br />

payments made for such work will not alter this position. The handing over by the Contractor<br />

and taking over by the Executive Engineer or his authorised representative will be always in<br />

writing copies of which will go to the Executive Engineer or his authorised representative and<br />

the Contractor. It is however, understood that before taking over such work, Government will<br />

not put it into regular use as distinct from casual or incidental one, expect as specifically<br />

mentioned elsewhere in this contract, or as mutually agreed to.<br />

6.10 ASSISTANCE IN PROCURING PRIORITIES, PERMITS ETC :<br />

The Engineer on a written request by Contractor will, if in his opinion the request is<br />

reasonable and in the interest of work and its progress, assist the Contractor in securing, the<br />

priorities for deliveries, transport, permits for controlled materials etc. where such are needed.<br />

The Department will not however be responsible for the non-availability of such facilities or<br />

delays on this behalf and no claims on account of such failure of delays shall be allowed by<br />

the Department.<br />

Signature of Contractor <strong>No</strong>. Of Corrections Executive Engineer