66 Dy. Executive Engineer<br />
11. TESTING ETC.:<br />
The Contractor shall be responsible for the quality of the work in the entire construction work<br />
within the contract. He shall, therefore, have his own independent and adequate setup for<br />
ensuring the same. This shall include establishing field laboratory for testing required for<br />
concrete works.<br />
12. AUTHORITIES OF THE ENGINEER IN CHARGE:<br />
Save in so far as it is legally or physically impossible the Contractor shall execute, complete<br />
and maintain the works in strict accordance with the contract under the directions and to the<br />
entire satisfaction of the Engineer in charge and shall comply with and adhere strictly to the<br />
Engineer-in-charge’s instructions and directions on any matter (Whether mentioned in the<br />
contract or not) pertaining to this works.<br />
The Engineer in charge shall decide all questions which may arise as to quality and<br />
acceptability of materials furnished and work executed, manner of execution, rate of progress<br />
of the works, interpretation of the plans and specifications and acceptability of fulfillment of<br />
the contract on the part of the Contractor . He shall determine the amount and quantity of<br />
work performed and materials furnished and his decision shall be final. In all such matters,<br />
and in any technical questions which may arise touching the contract, his decision shall be<br />
binding on the Contractor.<br />
The Engineer in charge shall have the power to enforce such decisions and orders if the<br />
Contractor fails to carry them out promptly. If the Contractor fails to execute the work ordered<br />
by the Engineer-in-charge . The Engineer in charge may give notice to Contractor specifying<br />
a reasonable period therein and on the expiry of that period proceed to execute such work as<br />
may be deemed necessary and recover the cost there of from the Contractor.<br />
12.1 AUTHORITIES OF THE ENGINEER-IN-CHARGE'S REPRESENTATIVE<br />
The duties of the representative of the Engineer-in-charge are to watch and supervise the<br />
work and to test and examine any material to be used for workmanship employed in<br />
connection with the works.<br />
12.2 The Engineer-in-charge may from time to time, in writing delegate to his representative any of<br />
the powers and authorities vested in the Engineer-in-charge and shall furnish to the<br />
Contractor a copy of all such delegations of powers and authorities. Any written instruction or<br />
approval given by the representative of the Engineer-in-charge to the Contractor within the<br />
terms of such delegations (but not otherwise) shall bind the Contractor and the Department as<br />
though it had been given by the Engineer-in-charge, provided always as follows.<br />
a) Failure of the representative of the Engineer-in-charge to disapprove any work or<br />
material shall not prejudice the power of the Engineer-in-charge there after to<br />
disapprove such work or materials and to order to pulling down, removal or breaking<br />
up thereof.<br />
b) If the Contractor is dissatisfied with any decision of the Representative of the<br />
Engineer-in-charge he shall be entitle to refer the matter to the Engineer-in-charge,<br />
who shall there upon confirm/reverse or vary such decision.<br />
13. LAY OUT OF WORK:<br />
Layout of the work will be done by the Contractor in consultation with the Executive Engineer<br />
of the Department or his representative, some permanent marks should however be<br />
established to indicate the demarcation of the structure or any component there of made to<br />
this permanent marks in measurement books and drawing signed by the contractor and the<br />
departmental officer, Responsibility regarding layout will be joint.<br />
14. SETTING OUT<br />
14.1 BUILDING WORKS :-<br />
The Engineer-in-charge shall furnish the contractor with only the four corners of the works site<br />
and a level bench mark and the contractor shall set out the works and shall provide an<br />
efficient staff for the purpose and shall be solely responsible for the accuracy of such setting<br />
out.<br />
Signature of Contractor <strong>No</strong>. Of Corrections Executive Engineer