70 Dy. Executive Engineer<br />
27. APPROVAL OF CONSTRUCTION MATERIALS AND CONSTRUCTION ACTIVITIES:<br />
Approval of all materials for the work shall be obtained in writing from Engineer-in-charge or<br />
his representative before its use in the Project.<br />
Before taking up of any construction activity the construction work done earlier shall be got<br />
approved in writing. Any failure on this account may result in the work for which the<br />
Contractor will be solely responsible.<br />
Materials and job mix, etc. shall be got approved in writing atleast 15 days in advanced of the<br />
commencement of the corresponding activity. The testing charges shall be borne by the<br />
Contractor.<br />
Besides the prescribed tests and frequencies any other test of tests over the prescribed<br />
frequency shall also be carried out by the Contractor at his own cost if so directed by<br />
Engineer-in-charge or his authorised representative.<br />
28. CONDITION RELATING TO INSURANCE OF CONTRACT WORK.<br />
Contractor shall take out necessary Insurance Policy/ (viz. Contractors All Risks Insurance<br />
Policy, Erection All Risks Insurance Policy etc. as decided by the Directorate of Insurance) so<br />
as to provide adequate insurance cover for execution of the awarded contract work for total<br />
contract value and complete contract period compulsorily from the “Directorate of Insurance,<br />
Maharashtra State, Mumbai only its postal address for Correspondence is “264, MHADA,<br />
First Floor, Opp. Kalanagar, Bandra (East) Mumbai – 400051” (Telephone <strong>No</strong>s. 26590403/<br />
26590690 and Fax <strong>No</strong>. 26592461/26590403) Similarly, all workmen’s appointed to complete<br />
the contract work are required to insure under workmen’s compensation insurance<br />
policy. Insurance policy/policies taken out from any other Company will not be accepted. If<br />
any contractor has effected Insurance with any insurance company the same will not be<br />
accepted and the amount of premium calculated by the Government Insurance Fund will be<br />
recovered directly from the amount payable to the Contractor for the executed contract work<br />
and paid to the Directorate of Insurance Fund, Maharashtra State, Mumbai, The Director of<br />
Insurance reserves the right to distribute the risks of insurance among the other insurers.<br />
29. DIARY:<br />
Contractor shall maintain, throughout the construction period, a diary in the from of a register<br />
regarding the following :-<br />
i) Daily presence of all categories of labours.<br />
ii) Daily availability and use of machinery and equipment’s on work.<br />
iii) Daily procurement, Consumption and balance of materials on site.<br />
iv) Daily record of various visiting authorities alongwith name of the officers visited and<br />
timing.<br />
v) Details of work executed per day. The register shall be closed on daily basis and<br />
signature of Engineers in charge or his representative should be taken over it.<br />
30. ADDITIONAL TECHNICAL CONDITIONS<br />
30.1 The work shall be carried out in the best workmanship like manner and in strict accordance<br />
with P.W.D. hand book Volume I & II 1960. Edition supplemented by specification attached<br />
and as per Standard Specifications Book of Government of Maharashtra of 1979 and as per<br />
specific order of the Executive Engineer or his representative from time to time.<br />
30.2 The orders issued by the Government in P.W. Department and the Superintending Engineer,<br />
Thane (P.W.) Circle, Thane from time to time regarding construction procedure shall be<br />
binding on the contractor in addition to the specification contained in P.W.D. hand book<br />
Volume I & II and book of standard specification of P.W. Department and the specifications<br />
enumerated above.<br />
30.3 The contractor shall submit day to day account of the materials issued to him and its use and<br />
also monthly progress and programme of work.<br />
30.4 a) The concrete mix design shall be got approved from Engineer in charge and the mix<br />
design shall give preliminary strength of 1.33 times working strength.<br />
Signature of Contractor <strong>No</strong>. Of Corrections Executive Engineer