01.11.2014 Views

B-1 AGREEMENT System Generated e-Tender No ... - e-Tendering

B-1 AGREEMENT System Generated e-Tender No ... - e-Tendering

B-1 AGREEMENT System Generated e-Tender No ... - e-Tendering

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

(F) FORMULA FOR CEMENT COMPONENT :-<br />

Where,<br />

V 6 = C 0 (Cl 1 - Cl 0 )<br />

---------------- x T<br />

Cl 0<br />

89 Dy. Executive Engineer<br />

V 6 = Amount of price escalation in Rupees to be allowed for Cement component.<br />

C 0 = Basic rate of cement in rupees per metric tonne as considered for working out value<br />

of P.<br />

Cl 1 = Average of cement Index published in the RBI Bulletin for the quarter under<br />

consideration.<br />

Cl 0 = Average of cement Index published in the RBI Bulletin for the quarter preceding the<br />

month in which to the last date prescribed for receipt of tender falls.<br />

T = Tonnage of cement used in the permanent works for the quarter under consideration.<br />

(G) FORMULA FOR C.I. / D.I. PIPE COMPONENT :-<br />

Where,<br />

V 6 = Q 0 (D 1 - D 0 )<br />

V 7 = Amount of price escalation in Rupees to be allowed for C.I. /D.I. Pipe component.<br />

D 0 = Pig Iron basic price in rupees per tonne as considered for working out value of P.<br />

D 1 = Average Pig Iron Price in upees per tonne during the quarter under consideration<br />

(published by IISCO)<br />

Q d = Tonnage of C.I./D.I. pipes used in the works during the quarter under consideration.<br />

The following conditions shall prevails:<br />

i. The operative period of the Contract shall mean the period commencing from the date of the<br />

work order issued to the Contractor and ending on the date on which the time allowed for<br />

completion of the works specified in the Contract for work expires, taking into consideration the<br />

extension of time, if any, for completion of the work granted by Engineer under the relevant<br />

clause of the Conditions of Contract in cases other than those where such extension is<br />

necessitated on account of default of the Contractor. The decision of the Engineer as regards the<br />

operative period of the Contract shall be final and binding on the Contractor. Where any<br />

compensation for liquidated damages is levied on the Contractor on account of delay in<br />

completion or inadequate progress under the relevant Contract provisions, the price adjustment<br />

amount for the balance work from the date of levy of such compensation shall be worked out by<br />

pagging the indices L 1 , M 1 , C 1 , P 1 , SI 1 to the levels corresponding to the date from which such<br />

compensation is levied.<br />

ii.<br />

This price variation clause shall be applicable to all contracts in B 1 , B 2 & C form but shall not<br />

apply for piece works. The price variation shall be determine during each quarter as per formula<br />

given above in this clause.<br />

iii. The price variation under the clause shall not be payable for the extra items required to be<br />

executed during the completion of the work and also on the excess quantities of items payable<br />

under the provisions Clause 38/37 of the contract from B 1 /B 2 respectively. Since the rates<br />

payable for the extra items or the extra quantities under Clause 38/37 are to be fixed as per the<br />

current DSR or as mutually agreed to yearly revision till completion of such work. In other words,<br />

when the completion / execution of extra items as well as extra quantities under Clause 38/37 of<br />

the contract from B 1 /B 2 extends beyond the operative date of the DSR then rates payable for the<br />

same beyond the date shall be revised with reference to the current DSR prevalent at that time<br />

on year to year basis or revised in accordance with mutual agreement thereon, as provided for in<br />

the Contract, whichever is less.<br />

Signature of Contractor <strong>No</strong>. Of Corrections Executive Engineer

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!