REWARI KANPUR PIPELINE<br />

PROJECT<br />

3 LAYER POLYETHYLENE COATING OF<br />

LINEPIPES<br />

DOCUMENT NUMBER<br />

0068-00-SPC-2004<br />

Revision 0<br />

6. Both 30 days and 48 hour tests shall be carried out for a particular material <strong>com</strong>bination<br />

and pipe diameter. In case results for 30 days test are satisfactory, subsequent coating<br />

application procedure qualification for different pipe size with same coating material<br />

<strong>com</strong>bination, 48 hours test shall be acceptable<br />

Table 5.3.2 : Testing Requirement During Production Coating<br />

Sl. No Test Testing Frequency<br />

Test Method<br />

and<br />

Acceptance<br />

Criteria<br />

Remarks<br />

a Degree of Cure One Pipe/Shift Section 5.3.1 Note 1, 2<br />

b Adhesion Tests One Pipe/ Shift Section 5.3.2 Note 1, 2<br />

One out of 25<br />

c Bond Strength<br />

Pipes Section 5.3.5 Note 1, 2<br />

d Impact Strength One Pipe/Shift Section 5.3.6 Note 1, 2<br />

e<br />

f<br />

Indentation<br />

Hardness<br />

Air Entrapment<br />

Test<br />

One Pipe/Shift Section 5.3.7 Note 1, 2<br />

One out of 25<br />

Pipes Section 5.3.10 Note 1, 2<br />

Thickness Measurements<br />

g<br />

Epoxy Layer<br />

Adhesive Layer<br />

Once in the beginning of<br />

Shift or whenever plant<br />

restart after stoppage<br />

Section 5.3.11 Note 1, 4<br />

Total Coating<br />

Thickness<br />

All Pipes<br />

h<br />

Holiday<br />

Inspection<br />

All Pipes Section 5.3.12 Note 1, 4<br />

i<br />

Cathodic<br />

Disbondment Test<br />

48 hour test at (+)<br />

65° C<br />

Once per week or each<br />

batch of epoxy used<br />

whichever is early<br />

Section 5.3.9 Note 1, 3<br />

Notes:<br />

1 Working shift shall be maximum 12 hours.<br />

2 In case the test fails to <strong>com</strong>ply the specified requirement, preceding and succeeding<br />

coated pipes shall be tested. If both pipes pass the test, then the remainder of the<br />

coated pipes in the lot shall be accepted. If tests on any one of the two pipes fail to<br />

meet the specified requirements then either all pipes shall be individually tested or<br />

0068-FMT-01 Page 21 of 31<br />