EPMC SERVICES FOR REWARI – KANPUR PIPELINE<br />

SCOPE OF WORK–PIPELINE LAYING AND ASSOCIATED WORKS<br />

3. WORK TENDERED<br />

3.1 Complete Scope of work desired to the tendered consists of the following:<br />

3.1.1 Laying of (18”) 457mm OD, 442.790km (approx.) long multi product pipeline from the Rewari<br />

Dispatch Terminal (RDT) to Kanpur Receipt terminal (KRT).<br />

3.1.2 Installation of pipeline at crossings of rail, road, utilities, underground pipelines and water<br />

bodies (river, canal, drain, nala etc.).<br />

3.1.3 Installation of scraper launching facilities within Despatch Terminal at Rewari, scraper<br />

receiving & launching facilities within Receipt Terminal at Bharatpur, Mathura, IP station of<br />

Sayyadpur pran & receiving facilities at Kanpur.<br />

3.1.4 Installation of 11 (Eleven) nos. of Sectionalizing Valve (SV) Stations on Rewari-Kanpur<br />

pipeline route and all associated facilities for civil, electrical, instrumentation, piping,<br />

mechanical as indicated in respective scope of works<br />

3.1.5 Supply of all materials as per Scope of supply.(Refer clause 5 of this specification)<br />

3.1.6 Carrying out associated mechanical, civil, structural, architectural, and electrical and<br />

instrumentation works for Saiyyadpur Pran and all SV station. Laying of optical fiber cable<br />

including additional 6” CS casings with 2 nos of HDPE pipe at cased / HDD crossings only.<br />

3.1.7 All works related to pre-testing, cleaning, magnetic cleaning, gauging, flushing, hydro-testing<br />

and swabbing pipeline section/ piping facilities.<br />

3.1.8 Carrying out all works related to magnetic cleaning & electronic geometric pigging (EGP) of<br />

entire pipeline.<br />

3.1.9 TCP & PCP) of pipeline and stations including design, supply & installation of TCP & PCP<br />

system as per details given in Electrical Scope of work.<br />

3.1.10 Pre-<strong>com</strong>missioning of pipeline sections, including providing <strong>com</strong>missioning assistance /<br />

support to HPCL for final <strong>com</strong>missioning of the entire pipeline and associated facilities.<br />

3.1.11 Idle time preservation of pipeline, as required.<br />

3.1.12 All statutory clearances, land acquisition for Anode bed stations (for TCP/PCP), SV-01 to SV-<br />

11 & Saiyyadpur Pran in the name of HPCL.<br />

3.1.13 Co-ordination/ Liasoning for realization of bank guarantee/ cash retention submitted by HPCL<br />

with various authorities for obtaining crossing permissions, <strong>com</strong>pensatory afforestation and<br />

maintenance as per the requirement of DFOs, restoration of ROU including obtaining NOCs<br />

from land owners/statutory authorities, etc.<br />

3.2 The total pipeline is divided two parts for execution. The work involved in each part is briefly<br />

described as under.<br />

n:\513-mh-2145-rkpl\23 exchange\pipeline laying tender-rkpl\final 16.04.2013\pipeline-1\01 sow\mh2145-c000-pl-sow-0001.doc<br />

MH2145-C000-PL-SOW-0001 RevA Page 6 of 42

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!