EPMC SERVICES FOR REWARI – KANPUR PIPELINE<br />

SPECIFICATION FOR PRE-COMMISSIONING OF PIPELINE SYSTEM<br />

5. PRE-COMMISSIONING ACT<strong>IV</strong>ITIES<br />

5.1 PRE-COMMISSIONING CHECKS<br />

5.1.1 Pre-<strong>com</strong>missioning checks shall be carried out for the pipeline system to ascertain that<br />

the pipeline system has been mechanically <strong>com</strong>pleted in all respect. These checks shall<br />

cover all the facilities of the main cross country pipeline starting from Rewari to Kanpur<br />

including, Receipt Stations, Sectionalizing Valve Stations, Intermediate Pigging Station as<br />

applicable. The pre-<strong>com</strong>missioning checks shall include the following:<br />

A. System Checks<br />

The entire facilities shall be checked against the latest P&ID's, Engineering and Vendor<br />

Drawings/Documents and other design specifications. Any short<strong>com</strong>ing observed shall be<br />

listed down in the form of punch lists and these should be duly attended or liquidated. The<br />

pipeline contractor should check the stations systems from the angle of pre-<strong>com</strong>missioning<br />

and <strong>com</strong>missioning and spell out any additional requirement of vents/drains, temporary<br />

arrangement/modification etc. that may be required during the pre-<strong>com</strong>missioning and<br />

<strong>com</strong>missioning activities and arrange for the same in consultation with the OWNER / WP<br />

representative.<br />

B. Checking of Field Instrument<br />

All the field instruments like actuated valves, shutdown valves, transmitters, solenoid valves,<br />

shut down switches, alarms etc. shall be checked physically and also for their intended<br />

application by simulating the actual conditions. It will also include checking of different<br />

meters, gauges, action of actuated valves, control valves, shutdown valves etc.<br />

C. Survey of the Pipelines<br />

This shall be performed to confirm that proper fittings/supports, Cathodic Protection system,<br />

route markets, warning signs, fencing around SV stations, etc. have been installed along the<br />

pipeline.<br />

D. Checking of Communication System<br />

This is to check that there is proper <strong>com</strong>munication with adequate back-up power to ensure<br />

uninterrupted <strong>com</strong>munication.<br />

E. Checking of Electrical Distribution System<br />

n:\513-mh-2145-rkpl\11 engineering\11.8 pipelines\06 spec\specification for pre-<strong>com</strong>missioning of pipeline<br />

system\mh2145-c000-pl-spc-0013.doc<br />

MH2145-C000-PL-SPC-0013 RevA Page 10 of 17

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!