REWARI KANPUR PIPELINE<br />

PROJECT<br />

HIGH FREQUENCY ELECTRIC WELDED<br />

(HFW) LINE PIPE<br />

DOCUMENT NUMBER<br />

0068-00-SPC-2002<br />

Revision 0<br />

The acceptance limit and disposition of lamination and other type of defects on the<br />

skelp/pipe body shall be as per Para E.5.5 of Annex-E and as modified in this<br />

specification.<br />

9.10.5 GEOMETRIC DEVIATIONS<br />

9.10.5.3 Dents on weld and heat affected zone (HAZ) are not acceptable.<br />

(New)<br />

9.10.6 HARD SPOTS<br />

Any hard spot having a minimum dimension greater than 2 in. (50.8 mm) in any direction<br />

and hardness greater than 248 HV10 shall be rejected. The section of pipe containing<br />

the hard spot shall be cut off and removed as a cylinder or entire pipe shall be rejected.<br />

9.10.7 OTHER SURFACE IMPERFECTIONS<br />

a) Imperfections that have a depth <br />

repaired in accordance with Para C.1 and as modified in this specification.<br />

b) Imperfections that have a depth > 0.05 t (measured from the surface) shall be<br />

classified as defect and shall be repaired in accordance with Para C.2 or C.3 and as<br />

modified in this spec.<br />

9.10.8 CRACKS, SWEATS AND LEAKS<br />

(New)<br />

Sections of the pipe containing cracks, sweats and leaks shall be cut off as per the<br />

requirement of API Spec 5L Para C.3 (b) or (c).<br />

9.10.9 OFFSET OF PLATE EDGES<br />

(New)<br />

All pipes shall be checked for offset of skelp edges. Offset shall be measured and<br />

recorded at least 3 times per operating shift (12 hours maximum).<br />

9.10.10 HEIGHT OF FLASH OF ELECTRIC WELDED PIPE<br />

(New) Each pipe shall be checked for conformance of height of flash. Height of flash shall be<br />

measured and recorded at least 3 times per operating shift (12 hours maximum).<br />

9.10.11 TRIM OF INSIDE FLASH OF ELECTRIC WELDED PIPE<br />

(New) Each pipe shall be checked for conformance of depth of trim. Depth of trim shall<br />

be measured and recorded at least 3 times per operating shift (12 hours<br />

maximum).<br />

9.11 DIMENSIONS, MASS AND TOLERANCES<br />

9.11.1.3 All pipes shall be supplied with length between 11.5 m and 12.5 m. However pipe with<br />

length between 10.0 m and 11.5 m can also be accepted for a max. of 5% of the<br />

ordered quantity. The minimum average length of the entire ordered quantity in any case<br />

shall be 12.0 m.<br />

0068-FMT-01 Page 11 of 38<br />

Copyright L&T-GULF Private Limited. All rights reserved.