EPMC SERVICES FOR REWARI – KANPUR PIPELINE<br />

SPECIFICATION FOR PIPELINE CONSTRUCTION<br />

4.13.3 Whenever the bottom of the trench contains projecting rocks which might damage the pipe or<br />

coating, the bottom of the trench shall be padded with a minimum of 4" (102 mm) of sand or soft soil to<br />

be furnished and installed by CONTRACTOR, all of which shall be approved by OWNER.<br />

4.13.4 The pipe shall be lowered into the trench as soon as the coating has hardened sufficiently so<br />

that the lowering will not cause holidays. This shall be checked by picking the pipe up after it has been<br />

lowered in and checking with a holiday detector. If this check shows holidays, the pipe must be lowered<br />

to skids until it has had sufficient time to properly harden.<br />

4.13.5 Wide non-abrasive slings, belts, or rubber tire and cradles shall be used in all lowering of the<br />

pipeline. The CONTRACTOR shall lower line in such a manner as to provide sufficient slack and to the<br />

satisfaction of OWNER. The line shall not be dropped or subjected to jar or impact.<br />

4.13.6 All coated and wrapped pipe, which has been supported in any manner, shall be subjected to<br />

close inspection and checked with a holiday detector to see that the coating is undamaged and if found<br />

damaged shall be patched.<br />

4.13.7 CONTRACTOR shall furnish sufficient proper equipment during the lowering-in operation to<br />

prevent bending of the pipe or damage to coating.<br />

4.13.8 Where ditch is excavated in rock, padding will be provided as specified in Clause 4.19 and 4.20<br />

entitled "Rock Trench and Earth Padding".<br />

4.13.9 Where multiple lines are installed in a <strong>com</strong>mon ditch, a minimum of 6 inch (15 cm) spacing shall<br />

separate the individual lines. Individually placed mounds of earth at approximately 20 foot (6 m)<br />

intervals shall be placed in the ditch between the lines prior to backfilling to assure separation of the<br />

lines.<br />

4.14 Backfill<br />

This shall include all work necessary to backfill excavated material in the ditch, and restore creek<br />

banks, hillsides, or other places where the right-of-way has been graded.<br />

4.14.1 Immediately after the pipe has been lowered, it shall be weighted by filling the ditch over the<br />

pipe with backfill material. After the ditch has been filled to the level of surrounding ground, one tread<br />

of a heavy tractor shall run over backfill to pack the backfill. This tamping operation is not to be done<br />

through rocky land where the coating might be damaged or through sections where drainage tile is<br />

encountered and might be damaged. After the above tamping operation, the remaining backfill shall be<br />

spread over the pipeline ditch in a manner acceptable to the OWNER and the land owner.<br />

4.14.2 Pipe, fittings, or appurtenances shall not be backfilled unless the pipe has the proper fit and the<br />

required cover and has been approved for backfill by OWNER.<br />

4.14.3 Where the pipe has been laid under streets, sidewalks, or railroads, backfill shall be done as set<br />

out in Clause 4.17 entitled Highway and Railway Crossings.<br />

n:\513-mh-2145-rkpl\11 engineering\11.8 pipelines\06 spec\specification for pipeline construction\mh2145-c000-<br />

pl-spc-0001.doc<br />

MH2145-C000-PL-SPC-0001 RevA Page 21 of 32