EPMC SERVICES FOR REWARI – KANPUR PIPELINE<br />

SPECIFICATION FOR PIPELINE CONSTRUCTION<br />

4. CONSTRUCTION<br />

4.1 Fences<br />

This shall include work done on all fences on the right-of-way which it may be<br />

necessary to cut to permit passage of equipment onto or along the right-of-way. All fences which have<br />

been cut shall be closed with gates constructed as set out in the drawings and in a manner acceptable<br />

to the OWNER.<br />

4.1.1 CONTRACTOR, having first ascertained from OWNER that permission has been secured from<br />

the property owner, shall furnish materials for and shall install a suitable, substantial gate or gap in<br />

every fence at the point of intersection of the proposed pipeline with the fence for access to land<br />

crossed by the line and for passage of construction equipment. Before cutting the fences to make<br />

these gates or gaps, CONTRACTOR shall brace and reinforce the fences on each side of the gap to<br />

be opened, in order to prevent damage to said fences. Gates or gaps shall be constructed that they<br />

can be securely closed and shall be the type specified by OWNER and shall satisfy land owner and<br />

tenant.<br />

CONTRACTOR shall furnish a watchman to maintain these gates where necessary to prevent<br />

livestock from entering or leaving the property or in any other instance where required by OWNER.<br />

CONTRACTOR will use only such roads through farms as are designated by property owners.<br />

4.1.2 CONTRACTOR shall furnish all wire, posts, nails, or other equipment for construction of<br />

temporary gates and repairing of fences.<br />

4.1.3 On <strong>com</strong>pletion of construction, the temporary gates shall be removed and fences restored by the<br />

CONTRACTOR to their original condition or better.<br />

4.2 Clearing<br />

This shall include work necessary for the clearing of all trees, brush, hedges, or other obstacles, with<br />

the exceptions noted below, lying within the confines of the right-of- way.<br />

4.2.1 Before clearing operations are started, CONTRACTOR shall familiarize itself with all special<br />

provisions included in the right-of-way easements secured by OWNER; and CONTRACTOR shall<br />

<strong>com</strong>ply with these provisions. Where the right-of-way passes over or through farm yards, groves,<br />

orchards, gardens, lawns, ditches, canals, or similar valuable property, then only that amount of rightof-way<br />

necessary for actual ditching and laying of pipe shall be used; and the CONTRACTOR shall<br />

perform the work in such places so as to minimize the damages and if necessary shall hand ditch or<br />

tunnel through such places.<br />

4.2.2 Where timber is encountered, CONTRACTOR shall clear the right-of-way by removal of all<br />

trees, brush, stumps, and other encumbrances. CONTRACTOR shall remove all brush, stumps, and<br />

n:\513-mh-2145-rkpl\11 engineering\11.8 pipelines\06 spec\specification for pipeline construction\mh2145-c000-<br />

pl-spc-0001.doc<br />

MH2145-C000-PL-SPC-0001 RevA Page 8 of 32