<strong>Plan</strong> for <strong>Technology</strong> Development<br />

7.4.3 <strong>Technology</strong> Demonstration Mirror<br />

Scope<br />

Although the mirror will be completed in March 2007, a critical milestone will be the delivery of<br />

the PSD for the coated TDM in September 2006. Earlier near term milestones are the delivery of<br />

the fused planar blank to ITT, from Corning, in April 2005 and the completion of slumped mirror<br />

in August 2005. From August 2005 to August 2006 the mirror will be fine ground and polished<br />

using small tool lap, full tool active lap, and ion beam figuring. The schedule for the TDM is<br />

given in Table 7-4.<br />

State of the Art TRL 3<br />

The required mid-spatial frequency performance for the TDM has not been demonstrated on the<br />

scale needed for <strong>TPF</strong>. Smaller mirrors (with a higher areal density) have demonstrated the<br />

required MSF, but in the class of the TDM, the requirement has only been met over part of the<br />

MSF range.<br />

Table 7-4. <strong>Technology</strong> Demonstration Mirror Schedule<br />

<strong>Plan</strong>ned<br />

Completion<br />

Date<br />

<strong>Plan</strong>ned Activities Performance Targets TRL<br />

Pre-Phase A<br />

April 2005<br />

Delivery of fused planar blank<br />

from Corning to ITT<br />

CTE uniformity meets or exceeds requirement 3<br />

August 2005 Completion of slumped mirror Mirror is within 0.5mm of net shape and cell structures<br />

are not deformed due to slumping process<br />

4<br />

August 2006<br />

Delivery of PSD for coated<br />

TDM from ITT to JPL<br />

Mirror meets or exceeds spatial surface performance<br />

requirements as described in Table 7<br />

5<br />

Phase A<br />

March 2007 Mirror completed 5<br />