Chapter 7<br />
7.5 Structural, Thermal, and Spacecraft Testbeds<br />
7.5.1 Metrology Components<br />
Scope<br />
The baseline approach is to follow SIM progress on the external metrology truss development<br />
while periodically revisiting the project requirements. If for any reason SIM technology is<br />
deemed insufficient for <strong>TPF</strong>-C needs, this task will be expanded to address <strong>TPF</strong>-C requirements.<br />
In addition, as the verification plan matures, metrology requirements will emerge. Any<br />
necessary technology development activities will be captured in the next update to this plan. The<br />
schedule for metrology components is given in Table 7-11. The metrology components have<br />
achieved TRL 3.<br />
Table 7-11. Metrology Components Schedule<br />
<strong>Plan</strong>ned<br />
Completion<br />
Date<br />
<strong>Plan</strong>ned Activities Performance Targets TRL<br />
Pre-Phase A<br />
Study and monitor metrology sensing<br />
scheme based on SIM components<br />
3<br />
Phase A<br />
Implement metrology scheme on Closedloop<br />
Secondary Mirror Position Control<br />
Testbed.<br />
6 DOF control to ~50 nm over 24-hour<br />
timescale<br />
4<br />
120