zaobíde bez výluk<br />

The Railways of the Slovak Republic (ŽSR) invested 168.1 million EUR<br />

in modernization of railway infrastructure in 2008. Works on rail tracks<br />

could not be executed without closures or modifications in the train<br />

diagram. A long-term objective of ŽSR is a change of traction in the<br />

corridor No. V.<br />

One of the activities of ŽSR to improve conditions for intermodal transport<br />

is promotion of public terminals network, providing terminal services on<br />

a non-discriminatory basis with interconnection to logistics centres for<br />

the purpose of efficient provision of logistics services. By achieving these<br />

objectives, the Operational Program “Transport” - priority axis 3 shall<br />

be fulfilled. These terminals shall comply with the conditions of AGTC<br />

agreement.<br />

Construction of tri-modal terminal is being prepared in Bratislava; another<br />

terminals of intermodal transport will be in Košice, Žilina and Leopoldov.<br />

All terminals are located on the European transport routes and will<br />

offer the carriers in intermodal transport complete range of services.<br />

Construction is planned between 2009 and 2012.<br />

- The aim of ŽSR, in the field of railway reconstruction, is to achieve<br />

European parameters of rail tracks. Priority is given to factors such<br />

as traffic speed, punctuality, security, low costs, availability and<br />

interoperability – described the key elements from the viewpoint of<br />

customers in freight transport the Head of strategic management of ŽSR<br />

Miroslav Garaj.<br />

ŽSR has to ensure enough incomes to cover planned objectives. The<br />

economic crisis that will result in decrease in ŽSR revenues from<br />

infrastructure charges by approximately 43 million EUR in 2009, had<br />

an impact on neighbouring railways as well. - ŽSR expect that current,<br />

average decline in performances by 35 percent should come to an<br />

end and for the upcoming years, a slight increase in performances is<br />

anticipated – concluded his presentation on strategy of ŽSR in the field of<br />

railway infrastructure modernization and its impact on freight transport in<br />

a conference “Trade year 2010” of <strong>ZSSK</strong> <strong>CARGO</strong> Miroslav Garaj.<br />

Miroslav Garaj, Monika SCHMIDTOVÁ<br />

Photo Vladimír SALZER<br />

Key activities of ŽSR in 2009<br />

ongoing modernization of the section of corridor VI Žilina – Krásno nad<br />

Kysucou,<br />

in March 2009, modernization of section Va Piešťany – Nové Mesto nad<br />

Váhom was completed,<br />

public tender for selection of the contractor for section Nové Mesto nad<br />

Váhom – Zlatovce (03/2010) and Zlatovce – Trenčianska Teplá was put<br />

out,<br />

in the second half-year, the completion of station Žilina Teplička<br />

commenced (2009 - 2011),<br />

design preparation of the modernization of section Liptovský Mikuláš –<br />

Košice is in progress (or possibly, optimization of section 140 km/h),<br />

RWSt. Poprad Tatry – modernization of platforms, II. stage.<br />

Planned activities of ŽSR for 2010 – 2015 (the most important projects)<br />

works on constructions, which commenced in 2009, should be in<br />

progress,<br />

modernization of building units and operating sets in the railway station<br />

Čierna nad Tisou,<br />

commencement of works on the constructions within TEN T 17 as a part<br />

of axis Paris – Vienna – Bratislava,<br />

modernization of rail track Kúty, state border – Bratislava Lamač up to<br />

160 km/h and interlocking system to ETCS level,<br />

implementation of GSM-R Bratislava – Žilina – Čadca,<br />

implementation of the ERTMS system in Corridor E (Dresden – Prague –<br />

Bratislava/Vienna – Budapest– Bucharest – Constanta),<br />

long-term objective of ŽSR strategy – change in traction in corridor V –<br />

transport branch Bratislava – Žilina after 2015.<br />

Kalingrad<br />

Minsk<br />

Warsava<br />

Katovice<br />

Žilina<br />

Bratislava<br />

Budapest<br />

Miskolc<br />

Bukurest<br />

Sarajevo<br />

Sofia<br />

22/23