APPENDIX B<br />

CONSTRUCTION COST <strong>AND</strong> PRODUCTIVITY IN <strong>PORT</strong> DEVELOPMENT<br />

Cost Estimation for Standardized Facilities<br />

The unit prices of the construction and the procurement of standardized facilities are<br />

estimated using past construction projects and cost estimations of other feasibility<br />

studies. The construction costs of each standardized facility per unit berth length (m) or<br />

unit wharf are summarized in the following tables:<br />

Table B.1<br />

Transshipment Type Port Terminal (-16 m Deep)<br />

Facilities Unit Dimension US$<br />

I. Infrastructure 30,500,000<br />

Berth Length m 350 17,500,000<br />

Depth m 16<br />

Terminal Area Marshalling Yard m 2 60,000<br />

CFS m 2 4,000,000<br />

Others m 2 40,000<br />

Earth Works Dredging m 3 1,000,000<br />

Reclamation m 3 100,000 9,000,000<br />

Slope Protection m 2 20,000<br />

II. Equipment 28,760,000<br />

Quay Crane 40t units 3<br />

Transfer Crane 40t units 12<br />

Side Lifter 40t units 4<br />

Tractor Head units 20<br />

Chassis units 40<br />

Forklift 5t units 8<br />

III. Management 4,090,000<br />

Office m 2 1,000<br />

Gate units 8<br />

Utilities LS 1<br />

IV. Related Facilities 5,000,000<br />

Access Road LS 1<br />

Pilotage LS 1<br />

Electric and Water Supply LS 1<br />

V. Total 68,350,000<br />