Technical Report No. 8 PORT AND SHIPPING
Technical Report No. 8 PORT AND SHIPPING
Technical Report No. 8 PORT AND SHIPPING
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
<strong>No</strong>tes: Planning base year is 2020. 1 TEU = 12 tons.<br />
Table B.8<br />
Liquid Bulk Wharf (-10 m Deep)<br />
Facilities Unit Dimension US$<br />
I. Infrastructure 3,390,000<br />
Berth Platform m 50<br />
Breast Dolphin units 6 1,540,000<br />
Mooring Dolphin units 2<br />
Access Way Trestles m 200 1,350,000<br />
Courseway m 300<br />
Earth Works Dredging m 3 100,000 500,000<br />
Reclamation m 3<br />
Slope Protection m 2<br />
II. Equipment 0<br />
III. Management 100,000<br />
Office LS 1<br />
Gate LS 1<br />
Utilities LS 1<br />
IV. Related Facilities 500,000<br />
Access Road LS 1<br />
Pilotage LS 1<br />
Electric & Water Supply LS 1<br />
V. Total 3,990,000<br />
Required Investment for the Development of Public Port<br />
Based on the required quantity of facilities and estimated costs, the total investment for<br />
the development of public ports is calculated by using productivity. Estimated port<br />
handling productivity by port type is assumed in the following table:<br />
Type<br />
Berth Size<br />
(Length/Depth: m)<br />
Table B.9<br />
Standard Productivity by Port Type<br />
Planned Capacity for Standard<br />
Operation (TEU or Ton/Year)<br />
B-6<br />
Planned Capacity for<br />
Initial Operation (TEU or<br />
Ton/Year)<br />
I 350/16 TEU 360,000 144,000<br />
Ton 4,320,000 1,728,000<br />
II 280/12 TEU 240,000 96,000<br />
Ton 2,880,000 1,152,000<br />
III 250/10 TEU 192,000 76,800<br />
Ton 2,304,000 921,600<br />
IV 170/10 Ton 340,000 136,000<br />
V 130/7.5 Ton 130,000 52,000<br />
VI 80/5 Ton 80,000 32,000<br />
VII -/12 Ton 3,000,000 1,200,000<br />
VIII -/10 Ton 1,500,000 600,000