12.07.2015 Views

Defining CCS Ready: An Approach to An International Definition

Defining CCS Ready: An Approach to An International Definition

Defining CCS Ready: An Approach to An International Definition

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Chapter 2: Capture <strong>Ready</strong> Plant <strong>Definition</strong>incremental capital cost for several different Capture <strong>Ready</strong> design options are described inmore detail in Appendix B.In addition <strong>to</strong> capital cost assessments, the level of effort (human labour) needed <strong>to</strong> meetthe requirements of a <strong>CCS</strong> <strong>Ready</strong> policy in a jurisdiction will also affect the cost of aCapture <strong>Ready</strong> plant. Exhibit 2-5 provides estimated levels of effort (in units of work-years)that project developers may have <strong>to</strong> expend <strong>to</strong> meet <strong>CCS</strong> <strong>Ready</strong> requirements. A level ofeffort is provided for each component for a Capture <strong>Ready</strong> Plant, as introduced in Exhibit 1-4 in Chapter 1. These estimates are tentative, and the specific level of effort will depend onthe content and depth of work performed by a project developer <strong>to</strong> meet a specified levelof readiness. The range of estimated level of effort shown in Exhibit 2-5 indicates thisvariation. In general, most Capture <strong>Ready</strong> activities will not take longer than two workyears. It is also important <strong>to</strong> recognize that the expended effort will not be sequential or ina single time block. It is most likely that the effort will be spread out over several calendaryears, as would the development of any BAU plant. In general, the activities related <strong>to</strong> thedevelopment of a Capture <strong>Ready</strong> plant are integral with the overall plant design andengineering. It is likely that much of the work needed <strong>to</strong> be Capture <strong>Ready</strong> could beaccomplished in the time it would take for a BAU plant <strong>to</strong> be designed and approved.Exhibit 2-5: Estimated Work Hours for Capture <strong>Ready</strong> ActivitiesEstimated Range of Work YearsCapture <strong>Ready</strong> Activities<strong>to</strong> Complete Activity aPlant Site Selection 0.2 – 0.5Technology Selection 0.5Design for Capture Facilities 1– 2Space Allowance 0.5 – 1Equipment Pre-investment 0.25 – 1Cost Estimate for Capture Facilities 1 – 2Environmental, Safety, and Other Approvals for Capture Facilities 1 – 2Public Awareness and Engagement Related <strong>to</strong> Eventual Capture Facilities 0.5 – 1Sources for Equipment, Materials, and Services for Capture Facilities 0.1 – 0.5Ongoing Obligations 0.1 – 0.2a Work Years is the <strong>to</strong>tal number of years of work required for all staff <strong>to</strong> complete the activity.Most project developers would consider developing Capture <strong>Ready</strong> plants <strong>to</strong> be within theirown purview, as the work involved is within the site boundary of the plant; however,transport and s<strong>to</strong>rage readiness will likely involve other entities with ownership rights <strong>to</strong> thetransport network or s<strong>to</strong>rage site. As highlighted in the Considerations and RecommendedPractices, it is expected that a developer will be required <strong>to</strong> show advancement or readinessin all aspects of <strong>CCS</strong> in order <strong>to</strong> get approval of its <strong>CCS</strong> <strong>Ready</strong> Plant. In this case, projectdevelopers would also have <strong>to</strong> consider the timing for being Transport- and S<strong>to</strong>rage <strong>Ready</strong>,as discussed below in later sections.2.4.2 Environmental, Safety, and Other ApprovalsMost countries have existing regulations that would require a wide variety of permits andother types of approvals at the planning, construction, and operational stages of a Capture<strong>Ready</strong> plant, as well as for retrofitting the plant with <strong>CCS</strong>. A <strong>CCS</strong> retrofit will result in23 February 2010 29

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!