BBBBflt] «BlJIUrIrlr - Clpdigital.org
BBBBflt] «BlJIUrIrlr - Clpdigital.org
BBBBflt] «BlJIUrIrlr - Clpdigital.org
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
24 F<strong>org</strong>ing - Stamping - Heat Treating<br />
E c o n o m i c a l H a n d l i n g o f M a t e r i a l *<br />
Material Handling, Comparison of the Electric Truck and Gaso<br />
line Tractor and the Design of Tote Boxes, Racks<br />
T H E F<strong>org</strong>e Department as usual, when a department<br />
of a manufacturing plant, was placed in the<br />
farthest corner of the property, away from the<br />
main buildings. The heat treat was added later near<br />
the machining departments as at that time most of the<br />
f<strong>org</strong>ings were heat treated after being rough machined.<br />
The steel shed is located next to the f<strong>org</strong>e<br />
shop with a 5-ton overhead crane which serves to unload<br />
cars, the shears under the shed and to deliver<br />
most of the heavy stock to hammers. The grinders<br />
and punch presses for cold trimming are in the f<strong>org</strong>e<br />
shop, the die room and f<strong>org</strong>e department machine shop<br />
are at one end, the tumbling room, inspection department<br />
and die storage at one side and the shipping department<br />
at the other end of the building.<br />
The steel yard under the crane is 57 ft. wide by 352<br />
ft. long, has held 3,000 tons steel stacked at random<br />
leaving no room to get around. At present racks are<br />
being built which will increase the capacity of the yard<br />
over 100 per cent allowing space for railroad track to<br />
run full length of shed and room to get around each<br />
pile for inspection or checking purposes. The racks<br />
are built of pipe placed in a concrete base. The pipes<br />
have about 4 ft. centers. The racks are laid out to<br />
take steel 20 ft. long leaving an open space of 4 ft. between<br />
each end of piles and vacant space has been left<br />
for steel that comes cut in short lengths and other<br />
wide enough to stack without racks.<br />
Stock for f<strong>org</strong>ings. Most of the heavier stock is<br />
delivered by crane to the large hammers in the row<br />
next to the steel shed, the stock being placed on skids<br />
under the crane slides over to the hammers. The balance<br />
of the stock is delivered on tote racks by electric<br />
lift trucks direct to the hammers and upsetting machines,<br />
the heaters working the stock from the racks<br />
into the furnaces.<br />
The flashings are handled in wheel barrows, a<br />
wheel barrow being placed at each hammer. When<br />
hammerman handles flash after f<strong>org</strong>ing is trimmed, he<br />
throws it in the wheelbarrow, if the flash and f<strong>org</strong>ing<br />
are pushed through the trimming press together. The<br />
checker when counting f<strong>org</strong>ings throws the flash into<br />
the wheel-barrow. One laborer on an average handles<br />
the flash from six hammers.<br />
After the stock is f<strong>org</strong>ed or upset the f<strong>org</strong>ings are<br />
handled in different ways, depending on the size and<br />
shape. Stock up-set for hammers is loaded on tote<br />
racks by the operator ready to move to the hammers.<br />
F<strong>org</strong>ings such as transmission gears, spiders, bevels<br />
and other small parts are counted into the tote box<br />
by the checker at the hammer. Levers, windshields<br />
and long light weight f<strong>org</strong>ings are placed on tote racks<br />
as checked. These f<strong>org</strong>ings are moved in tote boxes<br />
and racks by two electric lift trucks from the hammers<br />
and upsetting machines to the punch presses,<br />
and Trailers Comprehensively Discussed<br />
By E. TONKINf<br />
January, 1925<br />
tumbling room, inspecting department and to the shipping<br />
platform. At each operation that may be required<br />
on the f<strong>org</strong>ing, the operator works from the<br />
loaded container performing the operation, then placing<br />
the piece in an empty container. In this way,<br />
handling of f<strong>org</strong>ings except in performing some operation<br />
is eliminated. In addition to the two electric lift<br />
trucks used for moving racks and boxes there are hand<br />
lift trucks with same capacity and lift as the electric<br />
trucks located at the trimming presses, tumbling room<br />
and inspection department for use of operators to<br />
move containers short distances in case no electric<br />
trucks are available.<br />
The heavier f<strong>org</strong>ings such as truck gears and steering<br />
knuckles are counted by the checker into tractor<br />
trailers equipped with boxes. Crankshafts are loaded<br />
on special crankshaft tractor trailers. Axles both<br />
front and rear are also loaded on special axle tractor<br />
trailers. These trailers are moved by the gasoline<br />
tractor. The gears are taken to the punch presses<br />
if there is a center to punch out, then to the heat treat<br />
where they are worked from the trailers into the<br />
furnaces for heat treating, after heat treating and testing<br />
they are pickeled. From the pickling tank they<br />
are loaded directly into trailer and moved back to<br />
inspection department. The crankshafts go from the<br />
hammer to the upsetting machine then to the heat<br />
treat. At the heat treat they are loaded from trailers<br />
into furnaces, then from furnace to furnace, to testing,<br />
pickling, centering, straightening and as inspected, are<br />
loaded on trailers ready to ship. The axles are moved<br />
to the bulldozer for stretching to length after which<br />
they go to the heat treating; from the trailers they are<br />
loaded into furnaces, heat treated, and tested as loaded<br />
onto trailers then moved to f<strong>org</strong>e shop for straightening<br />
and inspection. An inspector works with the<br />
straightening gang and loads the axles as inspected.<br />
In this way all the heavy f<strong>org</strong>ings are delivered to<br />
shipping platform on trailers ready for shipping gang<br />
to load.<br />
The loading of cars is done by piecework. Thirtytwo<br />
and one-half cents per ton for automobile gears,<br />
levers, windshields and small parts. Twenty-four<br />
cents per ton for truck gears, knuckles and medium<br />
sized f<strong>org</strong>ings and 15c per ton for axles and crankshafts.<br />
These prices include openng the car doors,<br />
cleaning out the cars, placing and fastening the truck<br />
plates and closing the doors after the car is loaded.<br />
The loading gang consists of three men with one electric<br />
lift truck. One man looks after the gang and lines<br />
up the material to be loaded according to his list, while<br />
the other two, one of these driving the electric truck<br />
move the tote boxes, racks and trailers into the car.<br />
1 hese two men count the f<strong>org</strong>ings off at the same time<br />
being checked by the gang leader. The rate of pay is<br />
*Paper presented at a meeting of the American Drop divided F<strong>org</strong> among the three according to their responsiing<br />
Institute held at Pittsburgh. October 2 and 3. 1924. bilities The checker gets 36 per cent of tonnage, the<br />
tEngineer of Production, Union Switch & Signal Co. truck driver 33 per cent and the laborer gets 31 per