07.01.2013 Views

BBBBflt] «BlJIUrIrlr - Clpdigital.org

BBBBflt] «BlJIUrIrlr - Clpdigital.org

BBBBflt] «BlJIUrIrlr - Clpdigital.org

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

24 F<strong>org</strong>ing - Stamping - Heat Treating<br />

E c o n o m i c a l H a n d l i n g o f M a t e r i a l *<br />

Material Handling, Comparison of the Electric Truck and Gaso­<br />

line Tractor and the Design of Tote Boxes, Racks<br />

T H E F<strong>org</strong>e Department as usual, when a department<br />

of a manufacturing plant, was placed in the<br />

farthest corner of the property, away from the<br />

main buildings. The heat treat was added later near<br />

the machining departments as at that time most of the<br />

f<strong>org</strong>ings were heat treated after being rough machined.<br />

The steel shed is located next to the f<strong>org</strong>e<br />

shop with a 5-ton overhead crane which serves to unload<br />

cars, the shears under the shed and to deliver<br />

most of the heavy stock to hammers. The grinders<br />

and punch presses for cold trimming are in the f<strong>org</strong>e<br />

shop, the die room and f<strong>org</strong>e department machine shop<br />

are at one end, the tumbling room, inspection department<br />

and die storage at one side and the shipping department<br />

at the other end of the building.<br />

The steel yard under the crane is 57 ft. wide by 352<br />

ft. long, has held 3,000 tons steel stacked at random<br />

leaving no room to get around. At present racks are<br />

being built which will increase the capacity of the yard<br />

over 100 per cent allowing space for railroad track to<br />

run full length of shed and room to get around each<br />

pile for inspection or checking purposes. The racks<br />

are built of pipe placed in a concrete base. The pipes<br />

have about 4 ft. centers. The racks are laid out to<br />

take steel 20 ft. long leaving an open space of 4 ft. between<br />

each end of piles and vacant space has been left<br />

for steel that comes cut in short lengths and other<br />

wide enough to stack without racks.<br />

Stock for f<strong>org</strong>ings. Most of the heavier stock is<br />

delivered by crane to the large hammers in the row<br />

next to the steel shed, the stock being placed on skids<br />

under the crane slides over to the hammers. The balance<br />

of the stock is delivered on tote racks by electric<br />

lift trucks direct to the hammers and upsetting machines,<br />

the heaters working the stock from the racks<br />

into the furnaces.<br />

The flashings are handled in wheel barrows, a<br />

wheel barrow being placed at each hammer. When<br />

hammerman handles flash after f<strong>org</strong>ing is trimmed, he<br />

throws it in the wheelbarrow, if the flash and f<strong>org</strong>ing<br />

are pushed through the trimming press together. The<br />

checker when counting f<strong>org</strong>ings throws the flash into<br />

the wheel-barrow. One laborer on an average handles<br />

the flash from six hammers.<br />

After the stock is f<strong>org</strong>ed or upset the f<strong>org</strong>ings are<br />

handled in different ways, depending on the size and<br />

shape. Stock up-set for hammers is loaded on tote<br />

racks by the operator ready to move to the hammers.<br />

F<strong>org</strong>ings such as transmission gears, spiders, bevels<br />

and other small parts are counted into the tote box<br />

by the checker at the hammer. Levers, windshields<br />

and long light weight f<strong>org</strong>ings are placed on tote racks<br />

as checked. These f<strong>org</strong>ings are moved in tote boxes<br />

and racks by two electric lift trucks from the hammers<br />

and upsetting machines to the punch presses,<br />

and Trailers Comprehensively Discussed<br />

By E. TONKINf<br />

January, 1925<br />

tumbling room, inspecting department and to the shipping<br />

platform. At each operation that may be required<br />

on the f<strong>org</strong>ing, the operator works from the<br />

loaded container performing the operation, then placing<br />

the piece in an empty container. In this way,<br />

handling of f<strong>org</strong>ings except in performing some operation<br />

is eliminated. In addition to the two electric lift<br />

trucks used for moving racks and boxes there are hand<br />

lift trucks with same capacity and lift as the electric<br />

trucks located at the trimming presses, tumbling room<br />

and inspection department for use of operators to<br />

move containers short distances in case no electric<br />

trucks are available.<br />

The heavier f<strong>org</strong>ings such as truck gears and steering<br />

knuckles are counted by the checker into tractor<br />

trailers equipped with boxes. Crankshafts are loaded<br />

on special crankshaft tractor trailers. Axles both<br />

front and rear are also loaded on special axle tractor<br />

trailers. These trailers are moved by the gasoline<br />

tractor. The gears are taken to the punch presses<br />

if there is a center to punch out, then to the heat treat<br />

where they are worked from the trailers into the<br />

furnaces for heat treating, after heat treating and testing<br />

they are pickeled. From the pickling tank they<br />

are loaded directly into trailer and moved back to<br />

inspection department. The crankshafts go from the<br />

hammer to the upsetting machine then to the heat<br />

treat. At the heat treat they are loaded from trailers<br />

into furnaces, then from furnace to furnace, to testing,<br />

pickling, centering, straightening and as inspected, are<br />

loaded on trailers ready to ship. The axles are moved<br />

to the bulldozer for stretching to length after which<br />

they go to the heat treating; from the trailers they are<br />

loaded into furnaces, heat treated, and tested as loaded<br />

onto trailers then moved to f<strong>org</strong>e shop for straightening<br />

and inspection. An inspector works with the<br />

straightening gang and loads the axles as inspected.<br />

In this way all the heavy f<strong>org</strong>ings are delivered to<br />

shipping platform on trailers ready for shipping gang<br />

to load.<br />

The loading of cars is done by piecework. Thirtytwo<br />

and one-half cents per ton for automobile gears,<br />

levers, windshields and small parts. Twenty-four<br />

cents per ton for truck gears, knuckles and medium<br />

sized f<strong>org</strong>ings and 15c per ton for axles and crankshafts.<br />

These prices include openng the car doors,<br />

cleaning out the cars, placing and fastening the truck<br />

plates and closing the doors after the car is loaded.<br />

The loading gang consists of three men with one electric<br />

lift truck. One man looks after the gang and lines<br />

up the material to be loaded according to his list, while<br />

the other two, one of these driving the electric truck<br />

move the tote boxes, racks and trailers into the car.<br />

1 hese two men count the f<strong>org</strong>ings off at the same time<br />

being checked by the gang leader. The rate of pay is<br />

*Paper presented at a meeting of the American Drop divided F<strong>org</strong>­ among the three according to their responsiing<br />

Institute held at Pittsburgh. October 2 and 3. 1924. bilities The checker gets 36 per cent of tonnage, the<br />

tEngineer of Production, Union Switch & Signal Co. truck driver 33 per cent and the laborer gets 31 per

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!