3.2. Space needed for use <strong>and</strong> maintenance<br />
The e-Brick requires little maintenance following <strong>installation</strong> but clearance is required to allow<br />
adequate cooling of the internal electronics.<br />
Allow the following clearances (see Figure 5):<br />
>500mm from the air intake<br />
>300mm from the exhaust outlet<br />
>25mm from sides<br />
If the e-Brick will be mounted in an enclosure rather than in free air, it is essential that adequate<br />
ventilation is provided. Refer to Table 2 for the rated power dissipation for each product variant;<br />
this figure should be taken in to account when calculating overall system cooling requirements.<br />
e-Brick variant Power dissipation (W)<br />
3.6kW 300<br />
9kW 475<br />
12kW 900<br />
22kW 1500<br />
Table 2: Power dissipation<br />